442 S CROCKER ST 90013
Certificate Information: 442 S CROCKER ST 90013
- Application / Permit
- 23016-10000-19443
- Plan Check / Job No.
- B23LA10969
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (11) Homeless Shelter
- Work Description
- *eplan* (1) EMERGENCY HOMELESS SHELTER PER SECTION 12.81 LAFD DIRECTIVE NO.45 AND GOVERNMENT CODE SECTION 8698.et seq. (19 BEDS TOTAL) TENANT IMPROVEMENT FOR EXISTING WAREHOUSE AND OFFICE TO BE USED AS EMERGENCY HOMELESS SHELTER PER LAMC SECTION 12.81 LAFD DIRECTIVE NO.45 AND GOVERNMENT CODE SECTION 8698.et seq. (16 BEDS TOTAL)
- Permit Issued
- Issued on 3/8/2024
- Issuing Office
- Current Status
- CofO Issued on 8/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/20/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/22/2023 | VU NGUYEN |
| Corrections Issued | 7/5/2023 | VU NGUYEN |
| Quality Review Completed | 7/5/2023 | EUGENE BARBEAU |
| Applicant returned to address corrections | 10/23/2023 | VU NGUYEN |
| Applicant returned to address corrections | 1/30/2024 | VU NGUYEN |
| Applicant returned to address corrections | 2/27/2024 | VU NGUYEN |
| Plan Check Approved | 3/8/2024 | VU NGUYEN |
| Issued | 3/8/2024 | APPLICANT |
| TCO Issued (Expire Date: 07-23-2025) | 1/24/2025 | RAFAEL ESPINOZA |
| TCO Issued (Expire Date: 01-19-2026) | 7/23/2025 | ERNESTO CORRAL |
| CofO in Progress | 8/4/2025 | RAFAEL CORTES |
| CofO in Progress | 8/7/2025 | RAFAEL CORTES |
| Permit Finaled | 8/7/2025 | ERNESTO CORRAL |
| CofO Issued | 8/7/2025 | ERNESTO CORRAL |
| Permit Finaled | 8/7/2025 | ERNESTO CORRAL |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/2/2023 | WALLIE JONG |
| Sewer availability | Cleared | 8/2/2023 | WALLIE JONG |
| DAS Clearance | Cleared | 8/21/2023 | Eugene Barbeau |
| Fire Marshal Fire Life Safety | Cleared | 10/11/2023 | MENOA AGHAJANI |
| Miscellaneous | Cleared | 10/11/2023 | NOAH MCCOY |
| Green Code | Cleared | 10/12/2023 | Eugene Barbeau |
| Hydrant and Access approval | Cleared | 11/14/2023 | LAVEON RIDER |
Contact Information
| Architect | Yoo,, Ji-Ho; Lic. No.: C32900 | 1824 LOS ENCINOS AVE GLENDALE, CA 91208 |
| Contractor | Commercial Coating Company Inc; Lic. No.: 475564-A | P O BOX 65557 LOS ANGELES, CA 90065 |
| Engineer | Hwang,, Junho; Lic. No.: S5592 | 2450 W MAIN ST ALHAMBRA, CA 91801 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/10/2024 | Partial Approval | RAFAEL ESPINOZA |
| Insulation | 6/10/2024 | Partial Approval | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 7/18/2024 | Partial Approval | JAMES POWERS |
| Masonry Wall/Backfill | 8/7/2024 | Partial Approval | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 8/13/2024 | Partial Approval | RAFAEL ESPINOZA |
| Light Gage Steel Frame | 8/16/2024 | Partial Approval | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 8/21/2024 | Partial Approval | RAFAEL ESPINOZA |
| Insulation | 8/21/2024 | Approved | RAFAEL ESPINOZA |
| Light Gage Steel Frame | 8/21/2024 | Partial Approval | RAFAEL ESPINOZA |
| Deputy Wood Construction | 8/22/2024 | Conditional Approval | RAFAEL ESPINOZA |
| Drywall Nailing | 8/30/2024 | Not Ready for Inspection | JEFFREY FULTON |
| Drywall Nailing | 9/3/2024 | Partial Inspection | JEFFREY FULTON |
| Floor/Roof Diaphrgm/Shear Wall | 9/3/2024 | Partial Inspection | JEFFREY FULTON |
| Drywall Nailing | 9/6/2024 | Partial Approval | NICK DANERI |
| Footing/Foundation/Slab | 9/6/2024 | Partial Approval | NICK DANERI |
| Drywall Nailing | 9/19/2024 | Partial Approval | RAFAEL ESPINOZA |
| Interior/Exterior Lathing | 9/19/2024 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Interior/Exterior Lathing | 9/20/2024 | Partial Approval | RAFAEL CORTES |
| Light Gage Steel Frame | 9/27/2024 | Partial Approval | RAFAEL CORTES |
| Drywall Nailing | 10/8/2024 | Partial Approval | RAFAEL CORTES |
| Interior/Exterior Lathing | 10/10/2024 | Partial Approval | RAFAEL CORTES |
| T-Bar Ceiling | 10/22/2024 | Corrections Issued | RAFAEL CORTES |
| T-Bar Ceiling | 11/1/2024 | Partial Approval | NICK DANERI |
| Floor/Roof Diaphrgm/Shear Wall | 11/18/2024 | No Access for Inspection | RAFAEL CORTES |
| Final | 1/23/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Green Building Final | 1/23/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Green Building Rough | 1/23/2025 | Approved | RAFAEL CORTES |
| METHANE-Final | 1/23/2025 | Approved | RAFAEL CORTES |
| METHANE-Rough | 1/23/2025 | Approved | RAFAEL CORTES |
| Reinforced Masonry Frame | 1/23/2025 | Approved | RAFAEL CORTES |
| SGSOV-Seismic Gas S/O Valve | 1/23/2025 | SGSOV Approved | RAFAEL CORTES |
| Smoke Detectors | 1/23/2025 | Approved | RAFAEL CORTES |
| Final | 1/27/2025 | OK for TCO | RAFAEL CORTES |
| Green Building Final | 1/27/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Special/Order Compliance | 6/24/2025 | No Access for Inspection | RAFAEL CORTES |
| Special/Order Compliance | 6/26/2025 | Approved | RAFAEL CORTES |
| Final | 8/1/2025 | OK to Issue CofO | RAFAEL CORTES |
| Green Building Final | 8/1/2025 | Approved | RAFAEL CORTES |