800 E MARCO PL 90291

Certificate Information: 800 E MARCO PL 90291

Application / Permit
23016-10000-19222
Plan Check / Job No.
B23LA10828
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: REMODEL TO (E) SFD TO EXPAND ENTRY DOOR AND REVISE 1ST FLOOR FRAMING PLAN FOR DECK
Permit Issued
Issued on 5/29/2024
Issuing Office
Current Status
Permit Finaled on 4/7/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/12/2023 APPLICANT
Assigned to Plan Check Engineer 6/16/2023 JOHNPAUL ISIP
Corrections Issued 6/19/2023 JOHNPAUL ISIP
Applicant returned to address corrections 5/8/2024 JOHNPAUL ISIP
Plan Check Approved 5/24/2024 JOHNPAUL ISIP
Issued 5/29/2024 APPLICANT
Permit Finaled 4/1/2025 JESUS RODRIGUEZ

Permit Application Clearance Information

Coastal Zone Cleared 10/10/2023 RYAN LY
ZI Cleared 10/10/2023 RAFAEL FONTES
ZI Cleared 10/10/2023 RYAN LY
Specific Plan Cleared 5/6/2024 ALEX VELA

Contact Information

Contractor Emcee General Contracting; Lic. No.: 442286-B 21255 ENTRADA ROAD      TOPANGA, CA 90290
Engineer Niaki,, Neman; Lic. No.: C46030 1107 CALIFORNIA AVE #2      SANTA MONICA, CA 90403

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/31/2024 Partial Approval HERBERT GIRON
Footing/Foundation/Slab 11/6/2024 Partial Approval HERBERT GIRON
Deputy Drilled-In Anchors 11/20/2024 Conditional Approval HERBERT GIRON
Insulation 11/22/2024 Partial Approval HERBERT GIRON
Wood Frame 11/22/2024 Partial Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 12/2/2024 Partial Approval JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 12/4/2024 Partial Approval MICHAEL ALLEN
Insulation 12/4/2024 Approved MICHAEL ALLEN
Wall Anchors 12/4/2024 Approved MICHAEL ALLEN
Deputy Wood Construction 12/6/2024 Conditional Approval REGINA MENDEZ
Floor/Roof Diaphrgm/Shear Wall 12/12/2024 Corrections Issued HERBERT GIRON
Special/Order Compliance 12/12/2024 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 1/15/2025 Partial Approval HERBERT GIRON
Insulation 1/24/2025 Approved HERBERT GIRON
Interior/Exterior Lathing 1/24/2025 Partial Approval HERBERT GIRON
Wood Frame 1/24/2025 Partial Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 1/29/2025 Approved HERBERT GIRON
Special/Order Compliance 1/29/2025 Partial Approval HERBERT GIRON
Wood Frame 2/26/2025 Approved HERBERT GIRON
Final 4/1/2025 Permit Finaled JESUS RODRIGUEZ
Smoke Detectors 4/1/2025 Approved JESUS RODRIGUEZ