524 S LORRAINE BLVD 90020
Certificate Information: 524 S LORRAINE BLVD 90020
- Application / Permit
- 23016-10000-19200
- Plan Check / Job No.
- B23LA08908
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- ALTERATION TO EXISTING 1 STORY RECREATION ROOM AND 2 OF 3
- Permit Issued
- Issued on 10/10/2023
- Issuing Office
- Current Status
- Permit Finaled on 3/6/2025
Permit Application Status History
| Submitted | 5/12/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/1/2023 | CRYSTEL MAALOUF |
| Corrections Issued | 6/12/2023 | CRYSTEL MAALOUF |
| Quality Review Completed | 6/20/2023 | KEN GILL |
| Building Plans Picked Up | 6/28/2023 | APPLICANT |
| Plan Check Approved | 8/9/2023 | CRYSTEL MAALOUF |
| Issued | 10/10/2023 | APPLICANT |
| Permit Finaled | 3/6/2025 | JEFFREY MEAD |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 7/22/2023 | CELINA MORENO |
| Sewer availability | Cleared | 7/22/2023 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 7/27/2023 | CELINA MORENO |
| CPC | Cleared | 8/2/2023 | DAMIAN GATTO |
| CPC | Cleared | 8/2/2023 | DAMIAN GATTO |
| CPC | Cleared | 8/2/2023 | DAMIAN GATTO |
| HPOZ | Cleared | 8/2/2023 | DAMIAN GATTO |
| ZI | Cleared | 8/2/2023 | DAMIAN GATTO |
Contact Information
| Contractor | Vallernaud Construction Inc; Lic. No.: 1025929-B | 11513 W PICO BLVD LOS ANGELES, CA 90064 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/19/2024 | Approved | JEFFREY MEAD |
| Deputy Drilled-In Anchors | 6/10/2024 | Partial Approval | JEFFREY MEAD |
| BUILDING-Rough-Frame | 8/21/2024 | Approved | JEFFREY MEAD |
| ELECTRICAL-Rough | 8/21/2024 | Approved | JEFFREY MEAD |
| HVAC-Rough | 8/21/2024 | Approved | JEFFREY MEAD |
| PLUMBING-Rough | 8/21/2024 | Approved | JEFFREY MEAD |
| Drywall Nailing | 9/6/2024 | Approved | NICHOLAS LOPEZ |
| Interior/Exterior Lathing | 10/4/2024 | Not Ready for Inspection | ANTHONY RAMOS |
| Interior/Exterior Lathing | 11/12/2024 | Approved | NICHOLAS LOPEZ |
| ELECTRICAL-Final | 2/4/2025 | Approved | RONNIE MINDANAO |
| Gas Test | 2/4/2025 | Approved | RONNIE MINDANAO |
| HVAC-Final | 2/4/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| HVAC-Final | 2/6/2025 | Approved | JEFFREY MEAD |
| Final | 2/10/2025 | Corrections Issued | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 2/10/2025 | SGSOV Approved | JEFFREY MEAD |
| Smoke Detectors | 2/10/2025 | Approved | JEFFREY MEAD |
| Final | 2/14/2025 | Conditional Approval | JEFFREY MEAD |
| Final | 3/6/2025 | Permit Finaled | JEFFREY MEAD |