1127 W 81ST ST 90044

Certificate Information: 1127 W 81ST ST 90044

Application / Permit
23016-10000-19190
Plan Check / Job No.
B23LA10802
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan CONVERT (E) DETACHED GARAGE INTO ADU PER ORDINANCE.
Permit Issued
Issued on 9/15/2023
Issuing Office
Current Status
CofO Issued on 12/19/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/14/2023 APPLICANT
Assigned to Plan Check Engineer 6/21/2023 FERNANDO FLORES
Corrections Issued 6/22/2023 FERNANDO FLORES
Applicant returned to address corrections 8/3/2023 FERNANDO FLORES
Plan Check Approved 8/29/2023 MICHAEL LOPEZ
Issued 9/15/2023 APPLICANT
CofO in Progress 12/18/2025 MICHAEL LEWIS
Permit Finaled 12/19/2025 DEROLD HAUFF
CofO Issued 12/19/2025 DEROLD HAUFF
Permit Finaled 12/19/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/8/2023 JESSICA OPINION
Sewer availability Cleared 7/8/2023 JESSICA OPINION
Eng Process Fee Ord 176,300 Cleared 7/11/2023 JESSICA OPINION
Community Plan Implem. Overlay Cleared 7/26/2023 RAFAEL FONTES
Construction near power lines Cleared 8/26/2023 TINA MIRANDA

Contact Information

Contractor Owner-Builder       ,
Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 12/27/2024 Not Ready for Inspection JOHN QUINTANILLA
Footing/Foundation/Slab 12/27/2024 Corrections Issued JOHN QUINTANILLA
Underground Mechanical 12/27/2024 Approved JOHN QUINTANILLA
BUILDING-Rough-Frame 1/13/2025 Conditional Approval JOHN QUINTANILLA
ELECTRICAL-Rough 1/13/2025 Approved JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 1/13/2025 Partial Approval JOHN QUINTANILLA
Green Building Rough 1/13/2025 Not Ready for Inspection JOHN QUINTANILLA
HVAC-Rough 1/13/2025 Conditional Approval JOHN QUINTANILLA
PLUMBING-Rough 1/13/2025 Approved JOHN QUINTANILLA
Insulation 1/24/2025 Approved JOHN QUINTANILLA
Interior/Exterior Lathing 1/24/2025 Not Ready for Inspection JOHN QUINTANILLA
Drywall Nailing 3/4/2025 Corrections Issued JOHN QUINTANILLA
Drywall Nailing 3/6/2025 Approved JOHN QUINTANILLA
Interior/Exterior Lathing 3/6/2025 Approved JOHN QUINTANILLA
Interior/Exterior Lathing 3/18/2025 Corrections Issued JOHN QUINTANILLA
Shower Pan 3/18/2025 Approved JOHN QUINTANILLA
Interior/Exterior Lathing 4/11/2025 Approved ANTHONY RAMOS
Sewer 7/16/2025 Partial Approval JOHN QUINTANILLA
Sewer 7/18/2025 Approved RONNIE MEDINA
BUILDING-Rough-Frame 9/5/2025 Approved JOHN QUINTANILLA
Final 9/5/2025 Not Ready for Inspection JOHN QUINTANILLA
Green Building Final 9/5/2025 Not Ready for Inspection JOHN QUINTANILLA
Green Building Rough 9/5/2025 Approved JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 9/5/2025 SGSOV Not Ready JOHN QUINTANILLA
Smoke Detectors 9/5/2025 Not Ready for Inspection JOHN QUINTANILLA
Final 11/13/2025 Corrections Issued JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 11/13/2025 SGSOV Not Required JOHN QUINTANILLA
Smoke Detectors 11/13/2025 Approved JOHN QUINTANILLA
Final 12/17/2025 OK to Issue CofO MICHAEL LEWIS
Green Building Final 12/17/2025 Approved MICHAEL LEWIS