1483 W 186TH ST 90248
Certificate Information: 1483 W 186TH ST 90248
- Application / Permit
- 23016-10000-18992
- Plan Check / Job No.
- B23LA10658
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Interior remodel of (E) 1-story SFD. Scope to include demolition of non-loadbearing walls to create new floor layout. Re-roof with Class A or B roof covering material weighing less than 6 pounds per sq. ft. over existing solid sheathing. All work per WFPP. "Comply with Department Order effective date 01/21/2020."
- Permit Issued
- Issued on 6/21/2023
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 1/23/2024
Permit Application Status History
| Submitted | 6/8/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/8/2023 | VICTOR CHEN |
| Corrections Issued | 6/8/2023 | VICTOR CHEN |
| Plan Check Approved | 6/21/2023 | MICHAEL LANZONE |
| Issued | 6/21/2023 | APPLICANT |
| Permit Finaled | 1/23/2024 | NEVILLE REID |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Builder Point Construction; Lic. No.: 1059885-B | 11445 PARAMOUNT BLVD SUITE H DOWNEY, CA 90241 |
Inspector Information
| EDMUND LUM, (213) 252-3962 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUCIANO GAUNA, (213) 252-3962 | Office Hours: 7:00-8:00 AM MON-FRI |
| JAIME RIOS, (213) 252-3962 | Office Hours: 7:00-8:00 AM MON-FRI |
| ANDEY CHAPARRO, (213) 252-3962 | Office Hours: 7:00-8:00 AM MON-FRI |
| RYAN BARNES, (213) 252-3962 | Office Hours: 7:00-8:00 AM MON-FRI |
| PATRICK LIEBREGT, (213) 252-3962 | Office Hours: 7:00-8:00 AM MON-FRI |
| GLEN RAND, (213) 252-3962 | Office Hours: 7:00-8:00 AM MON-FRI |
| SHAWN ESHBACH, (213) 252-3962 | Office Hours: 7:00-8:00 AM MON-FRI |
| GABRIEL HERRERA, (213) 252-3962 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/14/2023 | Approved | NEVILLE REID |
| Underground Mechanical | 8/14/2023 | Partial Approval | NEVILLE REID |
| Rough-Elec/Plmb/HVAC | 8/31/2023 | Approved | NEVILLE REID |
| Sewer | 9/15/2023 | Approved | NEVILLE REID |
| Insulation | 10/4/2023 | Approved | NEVILLE REID |
| Drywall Nailing | 10/10/2023 | Approved | NEVILLE REID |
| Interior/Exterior Lathing | 10/10/2023 | Approved | NEVILLE REID |
| BUILDING-Rough-Frame | 1/10/2024 | Not Ready for Inspection | NEVILLE REID |
| ELECTRICAL-Final | 1/10/2024 | Not Ready for Inspection | NEVILLE REID |
| Final | 1/10/2024 | Not Ready for Inspection | NEVILLE REID |
| HVAC-Final | 1/10/2024 | Not Ready for Inspection | NEVILLE REID |
| MERV13>=Final | 1/10/2024 | Not Ready for Inspection | NEVILLE REID |
| MERV13>=Rough | 1/10/2024 | Not Ready for Inspection | NEVILLE REID |
| PLUMBING-Final | 1/10/2024 | Approved | NEVILLE REID |
| SGSOV-Seismic Gas S/O Valve | 1/10/2024 | SGSOV Not Ready | NEVILLE REID |
| Service/Power Release | 1/10/2024 | Not Ready for Inspection | NEVILLE REID |
| Smoke Detectors | 1/10/2024 | Approved | NEVILLE REID |
| Service/Power Release | 1/11/2024 | Approved | NEVILLE REID |
| Special/Order Compliance | 1/11/2024 | Approved | NEVILLE REID |
| ELECTRICAL-Final | 1/16/2024 | Approved | NEVILLE REID |
| HVAC-Final | 1/16/2024 | Approved | NEVILLE REID |
| MERV13>=Final | 1/16/2024 | Approved | NEVILLE REID |
| MERV13>=Rough | 1/16/2024 | Approved | NEVILLE REID |
| SGSOV-Seismic Gas S/O Valve | 1/16/2024 | SGSOV Approved | NEVILLE REID |
| BUILDING-Rough-Frame | 1/23/2024 | Approved | NEVILLE REID |
| Final | 1/23/2024 | Permit Finaled | NEVILLE REID |