6531 S SEPULVEDA BLVD 90045
Certificate Information: 6531 S SEPULVEDA BLVD 90045
- Application / Permit
- 23016-10000-18945
- Plan Check / Job No.
- B23LA10638
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- PROJECT HOMEKEY: MULTIFAMILY HOUSING PROGRAM PER GCS 50675.1.3. CONVERSION OF AN (E) 4 STORY 133 UNIT MOTEL INTO 118 LOW INCOME UNITS WITH SUPPORTIVE SERVICES AND 2 MANAGER'S UNITS. 120 UNITS TOTAL. 100% AFFORDABLE UNITS, NOT INCLUDING TWO MANAGER'S UNIT. CHANGE OF OCCUPANCY FROM R1 TO R2.
- Permit Issued
- Issued on 1/23/2024
- Issuing Office
- Current Status
- CofO Issued on 4/30/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/8/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/15/2023 | KEVIN MORALES |
| Corrections Issued | 6/23/2023 | KEVIN MORALES |
| Quality Review Completed | 6/27/2023 | EUGENE BARBEAU |
| Applicant returned to address corrections | 7/25/2023 | KEVIN MORALES |
| Applicant returned to address corrections | 8/24/2023 | KEVIN MORALES |
| Plan Check Approved | 12/28/2023 | KEVIN MORALES |
| Issued | 1/23/2024 | APPLICANT |
| CofO in Progress | 4/30/2026 | TED RIES |
| Permit Finaled | 4/30/2026 | TED RIES |
| CofO Issued | 4/30/2026 | TED RIES |
| Permit Finaled | 4/30/2026 | TED RIES |
Permit Application Clearance Information
| Miscellaneous | Cleared | 7/6/2023 | MAYELA VILLA |
| Eng Process Fee Ord 176,300 | Cleared | 7/11/2023 | DARIN LAM |
| Sewer availability | Cleared | 7/11/2023 | DARIN LAM |
| Specific Plan | Cleared | 8/1/2023 | EDUARDO HERMOSO |
| Miscellaneous | Cleared | 8/8/2023 | DANIEL CORONADO |
| Green Code | Cleared | 8/11/2023 | MICHAEL AYERS |
| Density Bonus | Cleared | 9/6/2023 | MARITES CUNANAN |
| Fire Marshal Fire Life Safety | Cleared | 11/27/2023 | MENOA AGHAJANI |
| Public Housing | Cleared | 12/6/2023 | DANIEL COLLINS |
| Low Impact Development (LID) | Cleared | 12/13/2023 | ORVAL HERNANDEZ-MARCI |
| DAS Clearance | Cleared | 12/21/2023 | ELIZABETH TOMS |
Contact Information
| Contractor | Benchmark Contractors Inc; Lic. No.: 462263-B | 3330 OCEAN PARK BLVD SANTA MONICA, CA 90405 |
Inspector Information
| DERRICK SPENCER, (310) 914-3919 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/14/2024 | No Access for Inspection | GRANT WOODS |
| Special/Order Compliance | 2/16/2024 | Approved | GRANT WOODS |
| Wood Frame | 2/21/2025 | Partial Inspection | AMANUEL BERHE |
| Wood Frame | 3/26/2025 | Partial Approval | RICARDO ROBLES |
| Drywall Nailing | 4/3/2025 | Partial Approval | VASIL MIHALEV |
| Drywall Nailing | 4/7/2025 | Partial Approval | VASIL MIHALEV |
| Wood Frame | 4/9/2025 | Not Ready for Inspection | RICARDO ROBLES |
| Light Gage Steel Frame | 4/18/2025 | Approved | VASIL MIHALEV |
| Wood Frame | 4/18/2025 | Approved | VASIL MIHALEV |
| Wood Frame | 4/21/2025 | Conditional Approval | MICHAEL PETRUSKO |
| Wood Frame | 4/22/2025 | Approved | MICHAEL PETRUSKO |
| Floor/Roof Diaphrgm/Shear Wall | 4/24/2025 | Approved | VASIL MIHALEV |
| Wood Frame | 4/28/2025 | Approved | VASIL MIHALEV |
| Insulation | 4/30/2025 | Approved | MICHAEL PETRUSKO |
| Drywall Nailing | 5/2/2025 | Approved | VASIL MIHALEV |
| Wood Frame | 5/2/2025 | Approved | VASIL MIHALEV |
| Wood Frame | 5/5/2025 | Approved | VASIL MIHALEV |
| Wood Frame | 5/14/2025 | Partial Approval | DERRICK SPENCER |
| Wood Frame | 5/21/2025 | Approved | MICHAEL PETRUSKO |
| Drywall Nailing | 5/28/2025 | Partial Approval | RICARDO ROBLES |
| Insulation | 5/29/2025 | Partial Approval | VASIL MIHALEV |
| Insulation | 6/3/2025 | Not Ready for Inspection | VASIL MIHALEV |
| Wood Frame | 6/3/2025 | Approved | VASIL MIHALEV |
| Insulation | 6/4/2025 | Approved | VASIL MIHALEV |
| Drywall Nailing | 6/10/2025 | Not Ready for Inspection | VASIL MIHALEV |
| Insulation | 6/10/2025 | Approved | VASIL MIHALEV |
| Wood Frame | 6/10/2025 | Approved | VASIL MIHALEV |
| Insulation | 6/11/2025 | Approved | VASIL MIHALEV |
| Drywall Nailing | 6/18/2025 | Approved | VASIL MIHALEV |
| Drywall Nailing | 7/14/2025 | Partial Approval | DANIEL VARNUM |
| Drywall Nailing | 7/16/2025 | Partial Approval | DERRICK SPENCER |
| Drywall Nailing | 8/13/2025 | Approved | VASIL MIHALEV |
| Light Gage Steel Frame | 8/13/2025 | Approved | VASIL MIHALEV |
| Light Gage Steel Frame | 8/15/2025 | Not Ready for Inspection | VASIL MIHALEV |
| Light Gage Steel Frame | 8/20/2025 | Approved | VASIL MIHALEV |
| Light Gage Steel Frame | 8/29/2025 | Not Ready for Inspection | NICK LAROCCA |
| Non Compliance | 8/29/2025 | Not Required | NICK LAROCCA |
| Wood Frame | 8/29/2025 | Not Ready for Inspection | NICK LAROCCA |
| Light Gage Steel Frame | 9/17/2025 | Approved | DERRICK SPENCER |
| Non Compliance | 9/17/2025 | Not Required | DERRICK SPENCER |
| Order to Comply | 9/17/2025 | Not Required | DERRICK SPENCER |
| Drywall Nailing | 9/25/2025 | Partial Approval | DERRICK SPENCER |
| Non Compliance | 9/25/2025 | Not Required | DERRICK SPENCER |
| Special/Order Compliance | 9/25/2025 | Approved | DERRICK SPENCER |
| Drywall Nailing | 10/2/2025 | Partial Approval | DERRICK SPENCER |
| Drywall Nailing | 10/20/2025 | Approved | DERRICK SPENCER |
| T-Bar Ceiling | 10/20/2025 | Partial Approval | DERRICK SPENCER |
| Insulation | 10/21/2025 | Approved | DERRICK SPENCER |
| Light Gage Steel Frame | 10/21/2025 | Approved | DERRICK SPENCER |
| Structural Steel Frame | 10/21/2025 | Approved | DERRICK SPENCER |
| Wood Frame | 10/21/2025 | Approved | DERRICK SPENCER |
| Drywall Nailing | 11/3/2025 | Approved | DERRICK SPENCER |
| Special/Order Compliance | 12/4/2025 | Approved | VASIL MIHALEV |
| Green Building Final | 1/16/2026 | Not Ready for Inspection | DERRICK SPENCER |
| Smoke Detectors | 1/16/2026 | Approved | DERRICK SPENCER |
| Final | 1/27/2026 | Not Ready for Inspection | DERRICK SPENCER |
| Green Building Final | 1/27/2026 | Approved | DERRICK SPENCER |
| METHANE-Final | 1/27/2026 | Approved | DERRICK SPENCER |
| SGSOV-Seismic Gas S/O Valve | 1/27/2026 | SGSOV Approved | DERRICK SPENCER |
| Final | 3/12/2026 | Not Ready for Inspection | DERRICK SPENCER |
| Pre-Inspection | 3/12/2026 | Approved | DERRICK SPENCER |
| Final | 4/30/2026 | OK to Issue CofO | TED RIES |