1046 1/4 W 84TH ST 90044

Certificate Information: 1046 1/4 W 84TH ST 90044

Application / Permit
23016-10000-18892
Plan Check / Job No.
B23LA10603
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
eplan Garage ADU Conversion. Convert three tandem garages within a three-story duplex into one ADU (ON GROUND LEVEL). ATTACHED ADU PER CA GOVT CODE 65852.2(e)(1)(C). NFPA 13D FIRE SPRINKLERS THROUGH OUT.
Permit Issued
Issued on 3/13/2024
Issuing Office
Current Status
CofO Issued on 6/4/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/9/2023 APPLICANT
Assigned to Plan Check Engineer 6/29/2023 ADRIANA LOPEZ
Corrections Issued 7/5/2023 ADRIANA LOPEZ
Quality Review Completed 7/7/2023 TU HUA
Applicant returned to address corrections 3/6/2024 ADRIANA LOPEZ
Plan Check Approved 3/12/2024 ADRIANA LOPEZ
Issued 3/13/2024 APPLICANT
CofO in Progress 5/7/2024 MICHAEL LEWIS
Permit Finaled 6/4/2024 DEROLD HAUFF
CofO Issued 6/4/2024 DEROLD HAUFF
Permit Finaled 6/4/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/5/2023 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 7/6/2023 JEANIE LAM
Sewer availability Cleared 7/6/2023 JEANIE LAM
Miscellaneous Cleared 7/10/2023 DAVID URITA

Contact Information

Architect Kelly,, Jonathan Stanleigh; Lic. No.: C34283 4819 TEMPLETON STREET      LOS ANGELES, CA 90032
Contractor Aardvark Group Inc The; Lic. No.: 762498-B       ,
Contractor The Aardvark Group Inc; Lic. No.: 762498-B       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Rough-Elec/Plmb/HVAC 3/18/2024 Corrections Issued MICHAEL LEWIS
Shower Pan 3/18/2024 Approved MICHAEL LEWIS
Interior/Exterior Lathing 3/19/2024 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 3/26/2024 Approved MICHAEL LEWIS
Green Building Rough 3/26/2024 Approved MICHAEL LEWIS
Insulation 3/26/2024 Approved MICHAEL LEWIS
Rough-Elec/Plmb/HVAC 3/26/2024 Approved MICHAEL LEWIS
Drywall Nailing 3/29/2024 Approved MICHAEL LEWIS
Final 4/24/2024 Corrections Issued MICHAEL LEWIS
Gas Test 4/24/2024 Approved MICHAEL LEWIS
Green Building Final 4/24/2024 Approved MICHAEL LEWIS
Rough-Elec/Plmb/HVAC 4/24/2024 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 4/24/2024 SGSOV Approved MICHAEL LEWIS
Service/Power Release 4/24/2024 Approved MICHAEL LEWIS
Smoke Detectors 4/24/2024 Approved MICHAEL LEWIS
Final 5/6/2024 OK to Issue CofO MICHAEL LEWIS