1821 N WILTON PL 90028

Certificate Information: 1821 N WILTON PL 90028

Application / Permit
23016-10000-18863
Plan Check / Job No.
B23LA10569
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN INTERIOR REMODELING FOR BOTH LEVELS 1 & 2. See Comments.
Permit Issued
Issued on 8/3/2023
Issuing Office
Current Status
Permit Finaled on 8/5/2025

Permit Application Status History

Submitted 6/7/2023 APPLICANT
Assigned to Plan Check Engineer 6/12/2023 ZAW HAN
Corrections Issued 6/13/2023 ZAW HAN
Applicant returned to address corrections 7/20/2023 ZAW HAN
Plan Check Approved 8/3/2023 JOSEPH RAFOLS
Issued 8/3/2023 APPLICANT
Permit Finaled 8/4/2025 CRAIG VAUGHAN

Permit Application Clearance Information

Sewer availability Cleared 7/3/2023 JESSICA OPINION
Eng Process Fee Ord 176,300 Cleared 7/5/2023 JESSICA OPINION
Grading Pre-Inspection Cleared 7/7/2023 SERGIO VALENZUELA
Specific Plan Cleared 7/17/2023 YAMILLET BRIZUELA

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/27/2023 Approved JOAQUIN GREENOUGH
PLUMBING-Rough 12/5/2023 Approved STUART CHAPMAN
Shower Pan 12/13/2023 Approved RAUL BARAJAS
ELECTRICAL-Rough 1/19/2024 Approved ROY SPAULDING
HVAC-Rough 1/19/2024 Corrections Issued ROY SPAULDING
HVAC-Rough 1/24/2024 Approved BRIAN SULLIVAN
BUILDING-Rough-Frame 1/30/2024 Conditional Approval BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 10/9/2024 Approved BRIAN SULLIVAN
BUILDING-Rough-Frame 10/22/2024 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 10/22/2024 Partial Approval BRIAN SULLIVAN
Rough-Elec/Plmb/HVAC 10/22/2024 Partial Approval BRIAN SULLIVAN
Insulation 10/28/2024 Approved CRAIG VAUGHAN
PLUMBING-Rough 10/28/2024 Approved CRAIG VAUGHAN
Drywall Nailing 11/1/2024 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 11/22/2024 Approved CRAIG VAUGHAN
Final 7/14/2025 Corrections Issued CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 7/14/2025 SGSOV Gas Company CRAIG VAUGHAN
Smoke Detectors 7/14/2025 Not Ready for Inspection CRAIG VAUGHAN
Final 7/21/2025 Corrections Issued CRAIG VAUGHAN
Smoke Detectors 7/21/2025 Approved CRAIG VAUGHAN
Final 7/29/2025 Not Ready for Inspection CRAIG VAUGHAN
Final 8/4/2025 Permit Finaled CRAIG VAUGHAN