5658 W AIRDROME ST 90019
Certificate Information: 5658 W AIRDROME ST 90019
- Application / Permit
- 23016-10000-18674
- Plan Check / Job No.
- B23LA10495
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan Convert existingdetached 4-car garage to Accessory Dwelling Unit per LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 10/3/2023
- Issuing Office
- Current Status
- Issued on 10/3/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/7/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/12/2023 | ANGELICA DAVE |
| Corrections Issued | 6/13/2023 | ANGELICA DAVE |
| Applicant returned to address corrections | 9/1/2023 | DANIEL YIP |
| Plan Check Approved | 9/28/2023 | FARSHAD ALIMOHAMADI |
| Issued | 10/3/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 7/11/2023 | JESSICA OPINION |
| Sewer availability | Cleared | 7/11/2023 | JESSICA OPINION |
| Eng Process Fee Ord 176,300 | Cleared | 8/17/2023 | JESSICA OPINION |
| Construction near power lines | Cleared | 9/23/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 9/23/2023 | RIDWAN HARDY |
Contact Information
| Architect | Terramorse,, William Dunwell; Lic. No.: C18265 | 513 COOLIDGE DRIVE SAN GABRIEL, CA 91775 |
| Contractor | Owner-Builder | , |
| Engineer | Bartelle,, Kristofer Grimm; Lic. No.: C84617 | 19900 ACRE ST LOS ANGELES, CA 91324 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/20/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 12/5/2023 | Partial Approval | RONNIE MINDANAO |
| ELECTRICAL-Rough | 12/14/2023 | Not Ready for Inspection | RONNIE MINDANAO |
| Footing/Foundation/Slab | 12/20/2023 | Conditional Approval | RONNIE MINDANAO |
| PLUMBING-Rough | 12/26/2023 | Partial Approval | RONNIE MINDANAO |
| Footing/Foundation/Slab | 1/2/2024 | Approved | BRENDAN MORELLI |
| Sewer | 1/2/2024 | Not Ready for Inspection | BRENDAN MORELLI |
| Pre-Inspection | 1/5/2024 | Partial Inspection | BRENDAN MORELLI |
| Sewer | 1/5/2024 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Rough | 1/18/2024 | Partial Approval | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 1/18/2024 | Partial Approval | BRENDAN MORELLI |
| Underground Mechanical | 1/18/2024 | Partial Approval | BRENDAN MORELLI |
| ELECTRICAL-Rough | 1/22/2024 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 1/22/2024 | Partial Approval | STUART CHAPMAN |
| Insulation | 1/25/2024 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 1/25/2024 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 1/30/2024 | Conditional Approval | BRENDAN MORELLI |
| Green Building Rough | 1/30/2024 | Not Ready for Inspection | BRENDAN MORELLI |
| Shower Pan | 1/30/2024 | Approved | BRENDAN MORELLI |
| Interior/Exterior Lathing | 2/26/2024 | Partial Approval | STUART CHAPMAN |
| BUILDING-Rough-Frame | 3/15/2024 | Approved | STUART CHAPMAN |
| Drywall Nailing | 3/15/2024 | Approved | STUART CHAPMAN |
| Final | 3/15/2024 | Corrections Issued | STUART CHAPMAN |
| Green Building Final | 3/15/2024 | Approved | STUART CHAPMAN |
| Green Building Rough | 3/15/2024 | Approved | STUART CHAPMAN |
| METHANE-Final | 3/15/2024 | Approved | STUART CHAPMAN |
| METHANE-Rough | 3/15/2024 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 3/15/2024 | SGSOV Not Ready | STUART CHAPMAN |
| Smoke Detectors | 3/15/2024 | Approved | STUART CHAPMAN |
| Final | 3/26/2024 | Conditional Approval | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 3/26/2024 | SGSOV Approved | ENRIQUE MIRELES |
| Service/Power Release | 3/26/2024 | Approved | ENRIQUE MIRELES |
| Wood Frame | 6/18/2025 | No Access for Inspection | ARTHUR NEGRETE |