1049 N OBAN DR 90065
Certificate Information: 1049 N OBAN DR 90065
- Application / Permit
- 23016-10000-18353
- Plan Check / Job No.
- B23LA10369
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 14'-10" X 6'-10" IRREGULAR SHAPED ADDITION AND REMODEL TO (E) S.F.D. PER ENGINEERING
- Permit Issued
- Issued on 8/25/2023
- Issuing Office
- Current Status
- CofO Issued on 10/25/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/5/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/9/2023 | DANIEL ABRAMYAN |
| Corrections Issued | 6/10/2023 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 8/1/2023 | ALFRED RAMIREZ |
| Plan Check Approved | 8/23/2023 | ALFRED RAMIREZ |
| Plan Check Approved | 8/24/2023 | ALFRED RAMIREZ |
| Issued | 8/25/2023 | APPLICANT |
| CofO in Progress | 10/22/2024 | THOMAS LOGRASSO |
| Permit Finaled | 10/25/2024 | RUBEN SALAS |
| CofO Issued | 10/25/2024 | RUBEN SALAS |
| Permit Finaled | 10/25/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/10/2023 | HUGO LOPEZ |
| Roof/Waste drainage to street | Cleared | 7/10/2023 | HUGO LOPEZ |
| Grading Pre-Inspection | Cleared | 8/1/2023 | DANIEL ABRAMYAN |
| Specific Plan | Cleared | 8/7/2023 | PABLO ESTRADA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Olson,, Allan James; Lic. No.: NA6722 | , |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/10/2024 | Corrections Issued | THOMAS LOGRASSO |
| Deputy Drilled-In Anchors | 6/4/2024 | Conditional Approval | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 6/5/2024 | Conditional Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 6/18/2024 | Partial Approval | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 6/27/2024 | Partial Approval | BRENDAN MORELLI |
| Insulation | 7/2/2024 | Not Ready for Inspection | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 7/8/2024 | Approved | THOMAS LOGRASSO |
| Special/Order Compliance | 7/8/2024 | Corrections Issued | THOMAS LOGRASSO |
| Drywall Nailing | 8/6/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Drywall Nailing | 8/8/2024 | Approved | THOMAS LOGRASSO |
| Final | 8/8/2024 | Corrections Issued | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 8/8/2024 | Approved | THOMAS LOGRASSO |
| Smoke Detectors | 8/8/2024 | Approved | THOMAS LOGRASSO |
| Wood Frame | 8/8/2024 | Approved | THOMAS LOGRASSO |
| Final | 8/12/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 10/21/2024 | OK to Issue CofO | THOMAS LOGRASSO |