2615 1/2 W SCOTT AVE 90026

Certificate Information: 2615 1/2 W SCOTT AVE 90026

Application / Permit
23016-10000-18234
Plan Check / Job No.
B23LA10308
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan. CONVERSION OF 330 SF PORTION OF EXISTING 400 SQ FT GARAGE INTO AN ACCESSORY DWELLING UNIT AND REMAINING 70 SF INTO STORAGE "COMPLY WITH DEPARTMENT ORDER effective date 04/20/2023. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 6/28/2023
Issuing Office
Current Status
CofO Issued on 3/10/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/5/2023 APPLICANT
Assigned to Plan Check Engineer 6/9/2023 JOSEPH RAFOLS
Corrections Issued 6/12/2023 JOSEPH RAFOLS
Plan Check Approved 6/27/2023 JOSEPH RAFOLS
Issued 6/28/2023 APPLICANT
No Progress 3/10/2025 DANIEL SANCHEZ
CofO in Progress 3/10/2025 DANIEL SANCHEZ
CofO in Progress 3/10/2025 ROBERT MINASSIANS
Permit Finaled 3/10/2025 DANIEL SANCHEZ
CofO Issued 3/10/2025 DANIEL SANCHEZ
Permit Finaled 3/10/2025 DANIEL SANCHEZ

Permit Application Clearance Information

Address approval Cleared 6/7/2023 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 6/7/2023 WALLIE JONG
Sewer availability Cleared 6/7/2023 WALLIE JONG
Grading Pre-Inspection Cleared 6/27/2023 JOSEPH RAFOLS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/17/2023 Approved COREY HUPP
Pre-Inspection 5/14/2024 Partial Approval EMIL OPFFER
Footing/Foundation/Slab 6/20/2024 Approved EMIL OPFFER
Pre-Inspection 6/20/2024 Approved EMIL OPFFER
ELECTRICAL-Rough 7/24/2024 Not Ready for Inspection COREY HUPP
HVAC-Rough 7/24/2024 Not Ready for Inspection COREY HUPP
PLUMBING-Rough 7/24/2024 Partial Approval COREY HUPP
Rough-Elec/Plmb/HVAC 8/1/2024 Partial Approval COREY HUPP
Rough-Elec/Plmb/HVAC 8/12/2024 Approved COREY HUPP
Insulation 8/15/2024 Approved JOEL ORDAZ
BUILDING-Rough-Frame 8/22/2024 Approved EMIL OPFFER
Green Building Rough 8/22/2024 Approved EMIL OPFFER
Insulation 8/22/2024 Approved EMIL OPFFER
Drywall Nailing 8/30/2024 Approved EMIL OPFFER
Interior/Exterior Lathing 9/24/2024 Partial Approval COREY HUPP
ELECTRICAL-Final 10/21/2024 Approved ROBERT NILES
Final 10/21/2024 Not Ready for Inspection ROBERT NILES
Green Building Final 10/21/2024 Approved ROBERT NILES
HVAC-Final 10/21/2024 Corrections Issued ROBERT NILES
PLUMBING-Final 10/21/2024 Corrections Issued ROBERT NILES
SGSOV-Seismic Gas S/O Valve 10/21/2024 SGSOV Approved ROBERT NILES
Smoke Detectors 10/21/2024 Approved ROBERT NILES
HVAC-Final 10/24/2024 Approved EMIL OPFFER
PLUMBING-Final 10/24/2024 Approved EMIL OPFFER
Final 11/5/2024 OK to Issue CofO ROBERT NILES