5741 S 11TH AVE 90043
Certificate Information: 5741 S 11TH AVE 90043
- Application / Permit
- 23016-10000-18228
- Plan Check / Job No.
- B23LA10299
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: CONVERT (E) 18'x18' DETACHED GARAGE WITH 14'x 7' ADDITION TO NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). WORK DONE PER ENGINEER.
- Permit Issued
- Issued on 3/13/2024
- Issuing Office
- Current Status
- Issued on 3/13/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/20/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/23/2023 | MIROOSH KHACHATOORIAN |
| Corrections Issued | 6/24/2023 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 12/9/2023 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 2/9/2024 | MIROOSH KHACHATOORIAN |
| Plan Check Approved | 2/21/2024 | MIROOSH KHACHATOORIAN |
| Issued | 3/13/2024 | APPLICANT |
Permit Application Clearance Information
| Sewer availability | Cleared | 8/7/2023 | NEIL TUANO |
| Address approval | Cleared | 8/9/2023 | NEIL TUANO |
| Eng Process Fee Ord 176,300 | Cleared | 8/9/2023 | NEIL TUANO |
| Roof/Waste drainage to street | Cleared | 8/9/2023 | NEIL TUANO |
| Construction within easement | Cleared | 12/1/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Medina,, Armando; Lic. No.: C83911 | 2000 W LINCOLN AVE MONTEBELLO, CA 90640 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/17/2024 | Corrections Issued | ANTHONY EGSON |
| Pre-Inspection | 2/27/2025 | Partial Approval | LUIS CASTRO |
| BUILDING-Rough-Frame | 3/18/2025 | Not Ready for Inspection | LUIS CASTRO |
| Footing/Foundation/Slab | 3/18/2025 | Corrections Issued | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 3/28/2025 | Partial Approval | LUIS CASTRO |
| ELECTRICAL-Rough | 5/9/2025 | Approved | LUIS CASTRO |
| PLUMBING-Rough | 5/9/2025 | Corrections Issued | LUIS CASTRO |
| BUILDING-Rough-Frame | 5/13/2025 | Conditional Approval | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 5/13/2025 | Conditional Approval | LUIS CASTRO |
| HVAC-Rough | 5/13/2025 | Approved | LUIS CASTRO |
| PLUMBING-Rough | 5/13/2025 | Approved | LUIS CASTRO |
| Insulation | 6/18/2025 | Partial Approval | LUIS CASTRO |
| Insulation | 6/23/2025 | Approved | LUIS CASTRO |
| Drywall Nailing | 12/31/2025 | Approved | ANTHONY RAMOS |
| Interior/Exterior Lathing | 12/31/2025 | Partial Approval | ANTHONY RAMOS |
| Drywall Nailing | 1/2/2026 | Approved | ANTHONY RAMOS |