431 W 7TH ST 7th floor 90014
Certificate Information: 431 W 7TH ST 7th floor 90014
- Application / Permit
- 23016-10000-18080
- Plan Check / Job No.
- B23LA10234
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (4) Gymnasium
- Work Description
- TENANT IMPROVEMENT AT THE 7TH FLOOR OF EXISTING PRIVATE ATHLETIC CLUB TO REMODEL FITNESS SPACES (A-3 OCCUPANCY, NO CHANGE OF USE).
- Permit Issued
- Issued on 8/30/2023
- Issuing Office
- Current Status
- Permit Finaled on 10/8/2024
Permit Application Status History
| Submitted | 6/2/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/9/2023 | SARKIS HARABEDIAN |
| Corrections Issued | 6/12/2023 | SARKIS HARABEDIAN |
| Applicant returned to address corrections | 7/17/2023 | JOE VO |
| Plan Check Approved | 8/30/2023 | SHANGQIN XIE |
| Issued | 8/30/2023 | APPLICANT |
| Permit Finaled | 10/8/2024 | JEROME BLACKWOOD |
Permit Application Clearance Information
| Fire Marshal Fire Life Safety | Cleared | 6/29/2023 | MENOA AGHAJANI |
| "D" conditions | Cleared | 6/30/2023 | DAVID URITA |
| Historic monument | Cleared | 7/27/2023 | LAMBERT GIESSINGER |
| Historic Resource Verification | Cleared | 7/31/2023 | MAX LODER |
| Redevelopment Project Area | Cleared | 8/15/2023 | SUSAN WONG |
Contact Information
| Architect | Liljegren,, Karin J; Lic. No.: NA28158 | , |
| Contractor | Itx Construction/Consultants Inc; Lic. No.: 621867-B | 245 FISCHER AVENUE SUITE D3 COSTA MESA, CA 92626 |
| Engineer | Youssef,, Nabih Fouad; Lic. No.: S2026 | 550 S HOPE ST STE 1700 LOS ANGELES, CA 90071 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 11/20/2023 | Partial Approval | KATY RAMIREZ |
| Drywall Nailing | 11/30/2023 | Partial Approval | KATY RAMIREZ |
| Light Gage Steel Frame | 11/30/2023 | Partial Approval | KATY RAMIREZ |
| Drywall Nailing | 12/6/2023 | Partial Approval | KATY RAMIREZ |
| Drywall Nailing | 12/11/2023 | Partial Inspection | KATY RAMIREZ |
| Light Gage Steel Frame | 12/11/2023 | Partial Approval | KATY RAMIREZ |
| Light Gage Steel Frame | 12/18/2023 | Partial Approval | JEROME BLACKWOOD |
| Drywall Nailing | 12/21/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| Light Gage Steel Frame | 12/21/2023 | Partial Approval | JEROME BLACKWOOD |
| Drywall Nailing | 1/3/2024 | Partial Approval | JEROME BLACKWOOD |
| Wood Frame | 1/5/2024 | Partial Approval | JEROME BLACKWOOD |
| Drywall Nailing | 1/8/2024 | Partial Approval | KATY RAMIREZ |
| Drywall Nailing | 1/10/2024 | Partial Approval | JEROME BLACKWOOD |
| Wood Frame | 1/12/2024 | Not Ready for Inspection | JEROME BLACKWOOD |
| Drywall Nailing | 1/16/2024 | Partial Approval | KATY RAMIREZ |
| Light Gage Steel Frame | 1/16/2024 | Partial Approval | KATY RAMIREZ |
| Drywall Nailing | 1/25/2024 | Partial Approval | JEROME BLACKWOOD |
| Wood Frame | 2/6/2024 | Partial Approval | JEROME BLACKWOOD |
| Drywall Nailing | 2/9/2024 | Partial Approval | KATY RAMIREZ |
| Drywall Nailing | 3/4/2024 | Approved | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 3/15/2024 | SGSOV Not Ready | LUIS CCAMACHO |
| Final | 9/11/2024 | Corrections Issued | LUIS CCAMACHO |
| SGSOV-Seismic Gas S/O Valve | 9/11/2024 | SGSOV Approved | LUIS CCAMACHO |
| Smoke Detectors | 9/11/2024 | Approved | LUIS CCAMACHO |
| Final | 10/8/2024 | Permit Finaled | JEROME BLACKWOOD |