555 S FLOWER ST 90071

Certificate Information: 555 S FLOWER ST 90071

Application / Permit
23016-10000-17922
Plan Check / Job No.
B23LA10173
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
TI @ 33RD FLOOR TO CREATE (3) CONFERENCE ROOMS W/ MOVABLE PARTITIONS. NEW DOOR AND INTERIOR OPENINGS BETWEEN OFFICES.
Permit Issued
Issued on 8/17/2023
Issuing Office
Current Status
Permit Finaled on 12/21/2023

Permit Application Status History

Submitted 6/1/2023 APPLICANT
Assigned to Plan Check Engineer 6/8/2023 JOE VO
Corrections Issued 6/26/2023 JOE VO
Quality Review Completed 6/27/2023 KEN GILL
Building Plans Picked Up 6/29/2023 APPLICANT
Green Plans Picked Up 7/5/2023 APPLICANT
Disabled Access Plans Picked Up 7/20/2023 APPLICANT
Plan Check Approved 8/17/2023 JOE VO
Issued 8/17/2023 APPLICANT
Permit Finaled 12/21/2023 KATY RAMIREZ

Permit Application Clearance Information

Green Code Cleared 8/1/2023 AARON COSTA
DAS Clearance Cleared 8/9/2023 JOE VO
Fire Marshal Fire Life Safety Cleared 8/9/2023 FIRE DEPARTMENT

Contact Information

Architect Conolly,, Christopher Mark; Lic. No.: C33137 17449 FRASER PLACE      GRANADA HILLS, CA 91344
Contractor Clune Construction Company L P; Lic. No.: 732107-B 725 SOUTH FIGUEROA STREET   STE 300    LOS ANGELES, CA 90017

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Light Gage Steel Frame 8/21/2023 Partial Approval ALFREDO LOPEZ
Drywall Nailing 8/24/2023 Partial Approval KATY RAMIREZ
Deputy Fireproofing 8/29/2023 Conditional Approval KATY RAMIREZ
Light Gage Steel Frame 9/5/2023 Corrections Issued RONALD JIMENEZ
Light Gage Steel Frame 9/7/2023 Partial Approval RAMAZANALI ALMASI
Drywall Nailing 9/8/2023 Partial Approval JULIAN CAPUCETTI
T-Bar Ceiling 9/19/2023 Partial Approval KATY RAMIREZ
Light Gage Steel Frame 11/6/2023 Partial Approval JEROME BLACKWOOD
Deputy Drilled-In Anchors 11/8/2023 Conditional Approval KATY RAMIREZ
Insulation 11/8/2023 Approved KATY RAMIREZ
Deputy Fireproofing 11/15/2023 Conditional Approval KATY RAMIREZ
Light Gage Steel Frame 11/21/2023 Partial Approval KATY RAMIREZ
Drywall Nailing 11/30/2023 Approved KATY RAMIREZ
T-Bar Ceiling 12/7/2023 Corrections Issued KATY RAMIREZ
Deputy Fireproofing 12/11/2023 Conditional Approval KATY RAMIREZ
Final 12/21/2023 Permit Finaled KATY RAMIREZ
Green Building Final 12/21/2023 Approved KATY RAMIREZ
SGSOV-Seismic Gas S/O Valve 12/21/2023 SGSOV No Gas KATY RAMIREZ
Smoke Detectors 12/21/2023 Approved KATY RAMIREZ