4166 W MELROSE AVE 90029
Certificate Information: 4166 W MELROSE AVE 90029
- Application / Permit
- 23016-10000-17916
- Plan Check / Job No.
- B23LA10165
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- TENANT IMPROVEMENT TO (E) RESTAURANT. WORK TO INCLUDE NEW CEILING, (N) KITCHEN EQUIPMENT, PARTITIONS, UPGRADE RESTROOMS FOR ACCESSIBILITY, FINISHES AND COUNTER.
- Permit Issued
- Issued on 5/2/2024
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 3/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/1/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/8/2023 | ZAW HAN |
| Corrections Issued | 6/13/2023 | ZAW HAN |
| Building Plans Picked Up | 6/14/2023 | APPLICANT |
| Plan Check Approved | 12/18/2023 | SAMUEL GONZALEZ |
| Issued | 5/2/2024 | APPLICANT |
| Permit Finaled | 3/7/2025 | LUIS CCAMACHO |
Permit Application Clearance Information
| Sewer availability | Cleared | 7/13/2023 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 7/14/2023 | JEANIE LAM |
| Specific Plan | Cleared | 11/7/2023 | YAMILLET BRIZUELA |
| Food Service Establishment | Cleared | 12/13/2023 | BOGDAN SERBANESCU |
| Food establishment approval | Cleared | 12/18/2023 | LACDHS APPROVED |
Contact Information
| Architect | Ong,, Francis Phat; Lic. No.: C18585 | 4122 GLENWOOD STREET IRVINE, CA 92604 |
| Contractor | C C K Builders Inc; Lic. No.: 855822-B | 625 WEST KATELLA AVENUE #2 ORANGE, CA 92867 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Drywall Nailing | 6/3/2024 | Partial Approval | RAFAEL CORTES |
| Wood Frame | 6/17/2024 | Partial Approval | RAMAZANALI ALMASI |
| Drywall Nailing | 7/1/2024 | Partial Approval | RAFAEL CORTES |
| Wood Frame | 7/1/2024 | Partial Approval | RAFAEL CORTES |
| Footing/Foundation/Slab | 7/22/2024 | Partial Approval | RAFAEL CORTES |
| Excavation/Setback/Form/Re-Bar | 7/23/2024 | Partial Approval | TIMOTHY POWELL |
| Wood Frame | 7/29/2024 | Partial Approval | RAMAZANALI ALMASI |
| Drywall Nailing | 7/30/2024 | Partial Approval | RAFAEL CORTES |
| Wood Frame | 7/30/2024 | Partial Approval | RAFAEL CORTES |
| T-Bar Ceiling | 8/1/2024 | Not Ready for Inspection | RAFAEL CORTES |
| Wood Frame | 8/1/2024 | Partial Approval | RAFAEL CORTES |
| Drywall Nailing | 8/2/2024 | Partial Approval | TIMOTHY POWELL |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2024 | Approved | RAFAEL CORTES |
| T-Bar Ceiling | 8/5/2024 | Partial Approval | RAFAEL CORTES |
| Wood Frame | 8/5/2024 | Approved | RAFAEL CORTES |
| Drywall Nailing | 8/6/2024 | Partial Approval | TIMOTHY POWELL |
| Interior/Exterior Lathing | 8/8/2024 | Partial Approval | RAFAEL CORTES |
| T-Bar Ceiling | 8/15/2024 | Partial Approval | RAFAEL CORTES |
| Final | 8/21/2024 | Not Ready for Inspection | RAFAEL CORTES |
| SGSOV-Seismic Gas S/O Valve | 8/21/2024 | SGSOV Not Ready | RAFAEL CORTES |
| Smoke Detectors | 8/21/2024 | Approved | RAFAEL CORTES |
| Final | 8/26/2024 | Corrections Issued | RAFAEL CORTES |
| SGSOV-Seismic Gas S/O Valve | 8/26/2024 | SGSOV Not Ready | RAFAEL CORTES |
| Final | 3/6/2025 | Partial Inspection | LUIS CCAMACHO |
| SGSOV-Seismic Gas S/O Valve | 3/6/2025 | SGSOV Approved | LUIS CCAMACHO |