13915 W LA MAIDA ST 91423
Certificate Information: 13915 W LA MAIDA ST 91423
- Application / Permit
- 23016-10000-17868
- Plan Check / Job No.
- B23LA10145
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) DETACHED GARAGE INTO A NEW ACCESSORY DWELLING UNIT (18'-2" x 20'-0") PER CA Govt. Code 65852.2(e)(1)(A).
- Permit Issued
- Issued on 6/26/2023
- Issuing Office
- Current Status
- CofO Issued on 2/9/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/1/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/7/2023 | SARKIS HARABEDIAN |
| Corrections Issued | 6/8/2023 | SARKIS HARABEDIAN |
| Plan Check Approved | 6/26/2023 | SARKIS HARABEDIAN |
| Issued | 6/26/2023 | APPLICANT |
| CofO in Progress | 1/12/2024 | MISAEL ESPARZA |
| Permit Finaled | 2/9/2024 | RUBEN SALAS |
| CofO Issued | 2/9/2024 | RUBEN SALAS |
| Permit Finaled | 2/9/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/12/2023 | LEE GUILBEAUX |
| Sewer availability | Cleared | 6/12/2023 | LEE GUILBEAUX |
| Construction near power lines | Cleared | 6/16/2023 | WALTER RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/20/2023 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yeghiayan,, Armond; Lic. No.: NA69935 | , |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/19/2023 | Conditional Approval | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 9/25/2023 | Approved | MISAEL ESPARZA |
| Footing/Foundation/Slab | 9/25/2023 | Approved | MISAEL ESPARZA |
| Pre-Inspection | 9/25/2023 | Approved | MISAEL ESPARZA |
| Sewer | 10/26/2023 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 11/6/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 11/6/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Sewer | 11/6/2023 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 11/17/2023 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 11/17/2023 | Corrections Issued | MISAEL ESPARZA |
| Sewer | 11/17/2023 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 11/21/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Rough | 11/21/2023 | Approved | MISAEL ESPARZA |
| Green Building Rough | 11/21/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 11/21/2023 | Approved | MISAEL ESPARZA |
| Sewer | 11/21/2023 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 11/27/2023 | Approved | MISAEL ESPARZA |
| HVAC-Rough | 11/27/2023 | Approved | MISAEL ESPARZA |
| Insulation | 11/28/2023 | Partial Approval | CHRISTOPHER ROJAS |
| Drywall Nailing | 12/1/2023 | Approved | KEVIN BERBERYAN |
| HVAC-Rough | 12/1/2023 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 12/1/2023 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 12/19/2023 | Approved | MISAEL ESPARZA |
| Final | 12/19/2023 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 12/19/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 12/19/2023 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 12/19/2023 | SGSOV Approved | MISAEL ESPARZA |
| Smoke Detectors | 12/19/2023 | Approved | MISAEL ESPARZA |
| Final | 12/22/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Final | 12/22/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Final | 1/11/2024 | OK to Issue CofO | MISAEL ESPARZA |
| Green Building Final | 1/11/2024 | Approved | MISAEL ESPARZA |