1011 N EVERETT ST Building A 90026
Certificate Information: 1011 N EVERETT ST Building A 90026
- Application / Permit
- 23016-10000-17849
- Plan Check / Job No.
- B23LA10135
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Attention: Quan Nghiem. Conversion of enclosed gym space to two ADUs.. BUILDING A.
- Permit Issued
- Issued on 9/22/2025
- Issuing Office
- Current Status
- CofO Issued on 2/17/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/8/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/8/2023 | QUAN NGHIEM |
| Corrections Issued | 6/21/2023 | QUAN NGHIEM |
| Quality Review Completed | 6/30/2023 | PETER KIM |
| Applicant returned to address corrections | 9/21/2023 | QUAN NGHIEM |
| Applicant returned to address corrections | 12/6/2023 | QUAN NGHIEM |
| Plan Check Approved | 2/8/2024 | QUAN NGHIEM |
| Issued | 9/22/2025 | APPLICANT |
| CofO in Progress | 2/17/2026 | RONALD JIMENEZ |
| Permit Finaled | 2/17/2026 | ERNESTO CORRAL |
| CofO Issued | 2/17/2026 | ERNESTO CORRAL |
| Permit Finaled | 2/17/2026 | ERNESTO CORRAL |
Permit Application Clearance Information
| Sewer availability | Cleared | 7/22/2023 | CELINA MORENO |
| "Q" conditions | Cleared | 7/26/2023 | MAYELA VILLA |
| Miscellaneous | Cleared | 7/26/2023 | MAYELA VILLA |
| Eng Process Fee Ord 176,300 | Cleared | 8/2/2023 | CELINA MORENO |
| Fire Marshal Fire Life Safety | Cleared | 9/26/2023 | MENOA AGHAJANI |
| Green Code | Cleared | 9/28/2023 | AARON COSTA |
| DAS Clearance | Cleared | 11/7/2023 | ELIZABETH TOMS |
Contact Information
| Architect | Epstein,, Matthew D; Lic. No.: C29433 | 18100 BURBANK BLVD #22 TARZANA, CA 91356 |
| Contractor | Dynamic Design Build Inc; Lic. No.: 747205-B | 11777 SAN VICENTE BLVD STE 800 LOS ANGELES, CA 90049 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/2/2025 | Corrections Issued | JEFFREY FULTON |
| Final | 2/17/2026 | OK to Issue CofO | RONALD JIMENEZ |
| Green Building Final | 2/17/2026 | Approved | RONALD JIMENEZ |
| Green Building Rough | 2/17/2026 | Approved | RONALD JIMENEZ |
| METHANE-Final | 2/17/2026 | Approved | RONALD JIMENEZ |
| METHANE-Rough | 2/17/2026 | Approved | RONALD JIMENEZ |
| Reinforced Concrete Frame | 2/17/2026 | Approved | RONALD JIMENEZ |
| SGSOV-Seismic Gas S/O Valve | 2/17/2026 | SGSOV Approved | RONALD JIMENEZ |
| Smoke Detectors | 2/17/2026 | Approved | RONALD JIMENEZ |
| Verify Sprinkler Sign Off | 2/17/2026 | Approved | RONALD JIMENEZ |
| Wood Frame | 2/17/2026 | Approved | RONALD JIMENEZ |