10743 W PICO BLVD 90064
Certificate Information: 10743 W PICO BLVD 90064
- Application / Permit
- 23016-10000-17516
- Plan Check / Job No.
- B23LA09929
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (18) Child Care Facility
- Work Description
- ePlan Change of use from retail/massage to daycare center, see comments
- Permit Issued
- Issued on 2/1/2024
- Issuing Office
- Current Status
- CofO Issued on 7/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/30/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/15/2023 | STARR CHEN |
| Corrections Issued | 6/16/2023 | RACHEL BEYENE |
| Quality Review Completed | 7/7/2023 | MICHAEL PEREZ |
| Applicant returned to address corrections | 12/8/2023 | RACHEL BEYENE |
| Applicant returned to address corrections | 1/24/2024 | STARR CHEN |
| Plan Check Approved | 1/31/2024 | STARR CHEN |
| Issued | 2/1/2024 | APPLICANT |
| Permit Finaled | 7/5/2024 | DAVID TSAU |
| CofO Issued | 7/5/2024 | DAVID TSAU |
| Permit Finaled | 7/5/2024 | DAVID TSAU |
Permit Application Clearance Information
| CPC | Cleared | 6/29/2023 | DAVID URITA |
| Miscellaneous | Cleared | 7/7/2023 | FADI ABBOUD |
| Eng Process Fee Ord 176,300 | Cleared | 7/25/2023 | DARIN LAM |
| Sewer availability | Cleared | 7/25/2023 | DARIN LAM |
| Miscellaneous | Cleared | 8/1/2023 | AHMED AMARRAGY |
| DAS Clearance | Cleared | 10/31/2023 | ELIZABETH TOMS |
| Specific Plan | Cleared | 11/13/2023 | ALESSANDRO MERCURI |
| Specific Plan | Cleared | 11/13/2023 | ALESSANDRO MERCURI |
| Specific Plan | Cleared | 1/17/2024 | JULISSA LOPEZ-HODOYAN |
| ZI | Cleared | 1/17/2024 | JULISSA LOPEZ-HODOYAN |
Contact Information
| Contractor | G - Pacific Development; Lic. No.: 1020036-B | , |
| Engineer | Yiu,, Siu; Lic. No.: S5801 | PO BOX 5143 EL MONTE, CA 91734 |
Inspector Information
| ROGELIO REYNA, (310) 914-3920 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/5/2024 | Conditional Approval | MICHAEL PETRUSKO |
| Final | 5/8/2024 | Not Ready for Inspection | MICHAEL PETRUSKO |
| METHANE-Final | 5/8/2024 | Not Ready for Inspection | MICHAEL PETRUSKO |
| SGSOV-Seismic Gas S/O Valve | 5/8/2024 | SGSOV Not Ready | MICHAEL PETRUSKO |
| Smoke Detectors | 5/8/2024 | Not Ready for Inspection | MICHAEL PETRUSKO |
| Final | 5/16/2024 | Conditional Approval | MICHAEL PETRUSKO |
| METHANE-Final | 5/16/2024 | Approved | MICHAEL PETRUSKO |
| SGSOV-Seismic Gas S/O Valve | 5/16/2024 | SGSOV Approved | MICHAEL PETRUSKO |
| Smoke Detectors | 5/16/2024 | Approved | MICHAEL PETRUSKO |