1902 W PARK AVE 116 90026

Certificate Information: 1902 W PARK AVE 116 90026

Application / Permit
23016-10000-17480
Plan Check / Job No.
B23LA09918
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: 1) CONVERT (E) HOBBY ROOM ON FIRST LEVEL INTO 578 SF ADU Per LAMC 12.22 A.33(c) and (e) 2) ENCLOSE COVERED PATIO OUTSIDE OF GYM INTO GYM CLASS SPACE OF 9'-10" X 25'-9"
Permit Issued
Issued on 10/21/2024
Issuing Office
Current Status
CofO Issued on 11/13/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/13/2023 APPLICANT
Assigned to Plan Check Engineer 6/29/2023 RAHEL BEYENE
Corrections Issued 6/30/2023 RAHEL BEYENE
Quality Review Completed 7/14/2023 MICHAEL PEREZ
Applicant returned to address corrections 8/21/2023 RAHEL BEYENE
Applicant returned to address corrections 10/19/2023 RAHEL BEYENE
Plan Check Approved 10/26/2023 RAHEL BEYENE
Issued 10/21/2024 APPLICANT
Permit Finaled 11/13/2025 ERNESTO CORRAL
CofO Issued 11/13/2025 ERNESTO CORRAL
Permit Finaled 11/13/2025 ERNESTO CORRAL

Permit Application Clearance Information

Miscellaneous Cleared 7/21/2023 MARITZA PRZEKOP
Miscellaneous Cleared 7/21/2023 MARITZA PRZEKOP
ZA Case Cleared 7/21/2023 MARITZA PRZEKOP
Address approval Cleared 7/22/2023 CELINA MORENO
Sewer availability Cleared 7/22/2023 CELINA MORENO
Supp. Use District POD/CDO/TDO Cleared 7/27/2023 ERICK MORALES
Eng Process Fee Ord 176,300 Cleared 8/8/2023 CELINA MORENO
DAS Clearance Cleared 10/3/2023 Sarkis Harabedian

Contact Information

Architect Makim,, Vaishali Harish; Lic. No.: C29964 2470 COLBY AVENUE      LOS ANGELES, CA 90064
Contractor Owner-Builder       ,
Engineer Funk,, David Lyle; Lic. No.: S5421 319 MAIN STREET      EL SEGUNDO, CA 90245

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/30/2024 Partial Inspection LUIS CCAMACHO
Light Gage Steel Frame 6/23/2025 Partial Approval LUIS CCAMACHO
Interior/Exterior Lathing 6/26/2025 Partial Approval LUIS CCAMACHO
Light Gage Steel Frame 7/9/2025 Partial Approval LUIS CCAMACHO
Drywall Nailing 7/15/2025 Partial Approval LUIS CCAMACHO
Final 9/2/2025 Not Ready for Inspection LUIS CCAMACHO
SGSOV-Seismic Gas S/O Valve 9/2/2025 SGSOV Approved LUIS CCAMACHO
Smoke Detectors 9/2/2025 Approved LUIS CCAMACHO
Verify Sprinkler Sign Off 9/2/2025 Approved LUIS CCAMACHO
Wood Frame 9/2/2025 Approved LUIS CCAMACHO
Final 11/12/2025 Partial Approval LUIS CCAMACHO