11926 W DOROTHY ST 90049
Certificate Information: 11926 W DOROTHY ST 90049
- Application / Permit
- 23016-10000-17452
- Plan Check / Job No.
- B23LA09898
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Eplan: Soft-Story seismic retrofit per LABC Chapter 93: By adding (1) new Special Steel Cantilever Column at the South elevation
- Permit Issued
- Issued on 9/6/2023
- Issuing Office
- Current Status
- Issued on 9/6/2023
Permit Application Status History
| Submitted | 5/30/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/8/2023 | HANS SANTIAGO |
| Corrections Issued | 6/12/2023 | HANS SANTIAGO |
| Quality Review Completed | 6/12/2023 | CHARLES CHANG |
| Applicant returned to address corrections | 8/3/2023 | HANS SANTIAGO |
| Plan Check Approved | 8/4/2023 | ANDREW SANTIAGO |
| Issued | 9/6/2023 | APPLICANT |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 9/5/2023 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Shaolian Sol K And Assoc Inc; Lic. No.: 720390-B | , |
| Contractor | Sks Construction; Lic. No.: 720390-B | , |
| Engineer | Shaolian,, Shahab Joseph; Lic. No.: C84155 | 15134 FRIAR ST VAN NUYS, CA 91411 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/10/2024 | Corrections Issued | DARRYL ARNOLD |
| Footing/Foundation/Slab | 6/13/2024 | Approved | RICARDO ROBLES |
| Wood Frame | 6/28/2024 | Approved | RICARDO ROBLES |
| Interior/Exterior Lathing | 7/8/2024 | Approved | JACOB MYERS |
| Final | 7/30/2024 | Not Ready for Inspection | RICARDO ROBLES |
| SGSOV-Seismic Gas S/O Valve | 7/30/2024 | SGSOV Not Ready | RICARDO ROBLES |
| Smoke Detectors | 7/30/2024 | No Access for Inspection | RICARDO ROBLES |
| Final | 9/27/2024 | Not Ready for Inspection | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 9/27/2024 | SGSOV Not Ready | DARRYL ARNOLD |
| Final | 11/18/2024 | Not Ready for Inspection | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 11/18/2024 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 11/18/2024 | Corrections Issued | DARRYL ARNOLD |
| Final | 12/9/2024 | Not Ready for Inspection | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 12/9/2024 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 12/9/2024 | Conditional Approval | DARRYL ARNOLD |