2135 1/4 N CANYON DR 90068
Certificate Information: 2135 1/4 N CANYON DR 90068
- Application / Permit
- 23016-10000-17282
- Plan Check / Job No.
- B23LA09819
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 18' X 46' DETACHED 4-CAR GARAGE TO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). WORK DONE PER ENGINEER.
- Permit Issued
- Issued on 8/11/2023
- Issuing Office
- Current Status
- CofO Issued on 7/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/30/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/5/2023 | MADISON ODELL |
| Corrections Issued | 6/5/2023 | MADISON ODELL |
| Applicant returned to address corrections | 7/21/2023 | MADISON ODELL |
| Applicant returned to address corrections | 7/27/2023 | ALFRED RAMIREZ |
| Applicant returned to address corrections | 7/28/2023 | MOHAMMAD ESMAILI |
| Plan Check Approved | 8/1/2023 | MOHAMMAD ESMAILI |
| Plan Check Approved | 8/11/2023 | ROSENDO MEDINA |
| Issued | 8/11/2023 | APPLICANT |
| CofO in Progress | 7/9/2025 | BRIAN SULLIVAN |
| Permit Finaled | 7/9/2025 | DEROLD HAUFF |
| CofO Issued | 7/9/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| ZI | Cleared | 6/9/2023 | RYAN LY |
| Address approval | Cleared | 6/22/2023 | JESSICA OPINION |
| Sewer availability | Cleared | 6/22/2023 | JESSICA OPINION |
| Watercourse | Cleared | 6/23/2023 | TERRY PHAN |
| Eng Process Fee Ord 176,300 | Cleared | 7/3/2023 | JESSICA OPINION |
| Grading Pre-Inspection | Cleared | 7/7/2023 | ROBERT HUGHES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Simonian,, Ara; Lic. No.: C37208 | 314 E BROADWAY STE A GLENDALE, CA 91205 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/9/2024 | Corrections Issued | BRENDAN MORELLI |
| Pre-Inspection | 8/13/2024 | Not Ready for Inspection | ROY SPAULDING |
| Pre-Inspection | 8/16/2024 | Not Ready for Inspection | ROY SPAULDING |
| PLUMBING-Rough | 8/28/2024 | Approved | ROY SPAULDING |
| Excavation/Setback/Form/Re-Bar | 9/5/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 9/5/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Sewer | 9/5/2024 | Approved | ALIZAH MAYAGOITIA |
| Underground Mechanical | 9/5/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Excavation/Setback/Form/Re-Bar | 9/9/2024 | Partial Approval | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 9/13/2024 | Approved | CRAIG VAUGHAN |
| Wood Frame | 10/4/2024 | Partial Approval | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 10/23/2024 | Partial Approval | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 10/23/2024 | Corrections Issued | CRAIG VAUGHAN |
| HVAC-Rough | 10/23/2024 | Partial Approval | CRAIG VAUGHAN |
| PLUMBING-Rough | 10/23/2024 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 11/20/2024 | Partial Approval | CRAIG VAUGHAN |
| HVAC-Rough | 11/20/2024 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 11/20/2024 | Partial Approval | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 12/3/2024 | Approved | CRAIG VAUGHAN |
| Insulation | 12/3/2024 | Approved | CRAIG VAUGHAN |
| Wood Frame | 12/3/2024 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 12/24/2024 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 1/21/2025 | Approved | WILLIAM SIERRA |
| ELECTRICAL-Final | 4/22/2025 | Corrections Issued | CRAIG VAUGHAN |
| Final | 4/22/2025 | Corrections Issued | CRAIG VAUGHAN |
| HVAC-Final | 4/22/2025 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 4/22/2025 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 4/22/2025 | SGSOV Approved | CRAIG VAUGHAN |
| Smoke Detectors | 4/22/2025 | Approved | CRAIG VAUGHAN |
| Final | 7/2/2025 | Not Ready for Inspection | BRIAN SULLIVAN |
| Final | 7/8/2025 | OK to Issue CofO | BRIAN SULLIVAN |
| Service/Power Release | 7/8/2025 | Approved | BRIAN SULLIVAN |