6941 N WILBUR AVE 91335
Certificate Information: 6941 N WILBUR AVE 91335
- Application / Permit
- 23016-10000-17176
- Plan Check / Job No.
- B23LA09757
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) ONE STORY DETACHED GARAGE INTO NEW ADU PER WFPP (Conversion of Accessory Building per State Law,CA Govt. Code 65852.2(e)(1)(A))
- Permit Issued
- Issued on 9/21/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/18/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/25/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/2/2023 | AUNG SOE |
| Corrections Issued | 6/7/2023 | AUNG SOE |
| Building Plans Picked Up | 6/8/2023 | APPLICANT |
| Plan Check Approved | 9/15/2023 | MINA HABILI |
| Issued | 9/21/2023 | APPLICANT |
| CofO in Progress | 1/3/2024 | JEFFREY BULL |
| Permit Finaled | 1/18/2024 | JOHN JANSON |
| CofO Issued | 1/18/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 6/20/2023 | LEE GUILBEAUX |
| Sewer availability | Cleared | 6/20/2023 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 6/21/2023 | LEE GUILBEAUX |
| ZI | Cleared | 8/28/2023 | DAVID URITA |
| Construction near power lines | Cleared | 9/12/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/17/2023 | Partial Approval | JEFFREY BULL |
| Sewer | 10/17/2023 | Not Ready for Inspection | JEFFREY BULL |
| Deputy Drilled-In Anchors | 10/19/2023 | Conditional Approval | JEFFREY BULL |
| Footing/Foundation/Slab | 10/20/2023 | Approved | JEFFREY BULL |
| Sewer | 10/20/2023 | Approved | JEFFREY BULL |
| Underground Mechanical | 10/26/2023 | Corrections Issued | HENRY KIM |
| ELECTRICAL-Rough | 11/6/2023 | Approved | JEFFREY BULL |
| PLUMBING-Rough | 11/6/2023 | Approved | JEFFREY BULL |
| BUILDING-Rough-Frame | 11/13/2023 | Approved | JEFFREY BULL |
| Green Building Rough | 11/13/2023 | Approved | JEFFREY BULL |
| HVAC-Rough | 11/13/2023 | Approved | JEFFREY BULL |
| Insulation | 11/13/2023 | Corrections Issued | JEFFREY BULL |
| Interior/Exterior Lathing | 11/13/2023 | Partial Approval | JEFFREY BULL |
| Insulation | 11/15/2023 | Approved | JEFFREY BULL |
| Interior/Exterior Lathing | 11/15/2023 | Approved | JEFFREY BULL |
| Shower Pan | 11/15/2023 | Approved | JEFFREY BULL |
| Drywall Nailing | 11/21/2023 | Approved | HENRY KIM |
| ELECTRICAL-Final | 1/2/2024 | Approved | JEFFREY BULL |
| Final | 1/2/2024 | OK to Issue CofO | JEFFREY BULL |
| Green Building Final | 1/2/2024 | Approved | JEFFREY BULL |
| HVAC-Final | 1/2/2024 | Approved | JEFFREY BULL |
| PLUMBING-Final | 1/2/2024 | Approved | JEFFREY BULL |
| SGSOV-Seismic Gas S/O Valve | 1/2/2024 | SGSOV Approved | JEFFREY BULL |
| Service/Power Release | 1/2/2024 | Approved | JEFFREY BULL |
| Smoke Detectors | 1/2/2024 | Approved | JEFFREY BULL |