6941 N WILBUR AVE 91335

Certificate Information: 6941 N WILBUR AVE 91335

Application / Permit
23016-10000-17176
Plan Check / Job No.
B23LA09757
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) ONE STORY DETACHED GARAGE INTO NEW ADU PER WFPP (Conversion of Accessory Building per State Law,CA Govt. Code 65852.2(e)(1)(A))
Permit Issued
Issued on 9/21/2023
Issuing Office
Valley
Current Status
CofO Issued on 1/18/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/25/2023 APPLICANT
Assigned to Plan Check Engineer 6/2/2023 AUNG SOE
Corrections Issued 6/7/2023 AUNG SOE
Building Plans Picked Up 6/8/2023 APPLICANT
Plan Check Approved 9/15/2023 MINA HABILI
Issued 9/21/2023 APPLICANT
CofO in Progress 1/3/2024 JEFFREY BULL
Permit Finaled 1/18/2024 JOHN JANSON
CofO Issued 1/18/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 6/20/2023 LEE GUILBEAUX
Sewer availability Cleared 6/20/2023 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 6/21/2023 LEE GUILBEAUX
ZI Cleared 8/28/2023 DAVID URITA
Construction near power lines Cleared 9/12/2023 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/17/2023 Partial Approval JEFFREY BULL
Sewer 10/17/2023 Not Ready for Inspection JEFFREY BULL
Deputy Drilled-In Anchors 10/19/2023 Conditional Approval JEFFREY BULL
Footing/Foundation/Slab 10/20/2023 Approved JEFFREY BULL
Sewer 10/20/2023 Approved JEFFREY BULL
Underground Mechanical 10/26/2023 Corrections Issued HENRY KIM
ELECTRICAL-Rough 11/6/2023 Approved JEFFREY BULL
PLUMBING-Rough 11/6/2023 Approved JEFFREY BULL
BUILDING-Rough-Frame 11/13/2023 Approved JEFFREY BULL
Green Building Rough 11/13/2023 Approved JEFFREY BULL
HVAC-Rough 11/13/2023 Approved JEFFREY BULL
Insulation 11/13/2023 Corrections Issued JEFFREY BULL
Interior/Exterior Lathing 11/13/2023 Partial Approval JEFFREY BULL
Insulation 11/15/2023 Approved JEFFREY BULL
Interior/Exterior Lathing 11/15/2023 Approved JEFFREY BULL
Shower Pan 11/15/2023 Approved JEFFREY BULL
Drywall Nailing 11/21/2023 Approved HENRY KIM
ELECTRICAL-Final 1/2/2024 Approved JEFFREY BULL
Final 1/2/2024 OK to Issue CofO JEFFREY BULL
Green Building Final 1/2/2024 Approved JEFFREY BULL
HVAC-Final 1/2/2024 Approved JEFFREY BULL
PLUMBING-Final 1/2/2024 Approved JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 1/2/2024 SGSOV Approved JEFFREY BULL
Service/Power Release 1/2/2024 Approved JEFFREY BULL
Smoke Detectors 1/2/2024 Approved JEFFREY BULL