ePlan: Detached Garage at Rear of lot conversion to an Accessory Dwelling Unit per CA Govt. Code 65852.2(e)(1)(A) using the 2023 Wood Frame Prescriptive Provisions (WFPP)
Permit Issued
Issued on 3/27/2024
Issuing Office
Current Status
CofO Issued on 5/21/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/25/2023 APPLICANT
Assigned to Plan Check Engineer 6/2/2023 EDWIN ESPIN
Corrections Issued 6/3/2023 EDWIN ESPIN
Applicant returned to address corrections 10/24/2023 EDWIN ESPIN
Applicant returned to address corrections 3/14/2024 CAROLEAN BASMA
Plan Check Approved 3/27/2024 CAROLEAN BASMA
Issued 3/27/2024 APPLICANT
CofO in Progress 5/2/2025 MISAEL ESPARZA
Permit Finaled 5/21/2025 RUBEN SALAS
CofO Issued 5/21/2025 RUBEN SALAS
Permit Finaled 5/21/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 10/23/2023 BRYAN GODINEZ
Sewer availability Cleared 10/23/2023 BRYAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 10/30/2023 BRYAN GODINEZ
ZI Cleared 11/16/2023 NELSON RODRIGUEZ
Construction near power lines Cleared 2/14/2024 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/30/2024 Partial Approval MISAEL ESPARZA
Sewer 7/30/2024 Not Ready for Inspection MISAEL ESPARZA
Underground Mechanical 7/30/2024 Partial Approval MISAEL ESPARZA
Footing/Foundation/Slab 8/2/2024 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 8/30/2024 Corrections Issued MISAEL ESPARZA
HVAC-Rough 8/30/2024 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 8/30/2024 Approved MISAEL ESPARZA
Sewer 9/19/2024 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 9/23/2024 Approved MISAEL ESPARZA
HVAC-Rough 9/23/2024 Not Ready for Inspection MISAEL ESPARZA
Sewer 9/23/2024 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 9/25/2024 Corrections Issued MISAEL ESPARZA
Green Building Rough 9/25/2024 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 9/25/2024 No Access for Inspection MISAEL ESPARZA
PLUMBING-Rough 10/22/2024 Approved MISAEL ESPARZA
Wood Frame 12/6/2024 Corrections Issued LOUIS ESCOTO
HVAC-Rough 12/12/2024 Approved JUAN VALENZUELA
Insulation 12/17/2024 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 12/24/2024 Approved JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 12/24/2024 Approved JUAN VALENZUELA
Green Building Rough 12/24/2024 Approved JUAN VALENZUELA
Drywall Nailing 1/6/2025 Approved MISAEL ESPARZA
Shower Pan 1/17/2025 Approved MISAEL ESPARZA
ELECTRICAL-Final 4/25/2025 Approved JAVIER RAMOS JR
Final 4/25/2025 Corrections Issued JAVIER RAMOS JR
Green Building Final 4/25/2025 Approved JAVIER RAMOS JR
HVAC-Final 4/25/2025 Approved JAVIER RAMOS JR
PLUMBING-Final 4/25/2025 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 4/25/2025 SGSOV Not Required JAVIER RAMOS JR
Smoke Detectors 4/25/2025 Approved JAVIER RAMOS JR
Final 4/30/2025 OK to Issue CofO MISAEL ESPARZA