1717 1/2 N PHILLIPS WAY 90042

Certificate Information: 1717 1/2 N PHILLIPS WAY 90042

Application / Permit
23016-10000-16862
Plan Check / Job No.
B23LA08038
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(E) DETACHED GARAGE CONVERSION INTO ADU PER LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 2/6/2024
Issuing Office
Current Status
CofO Issued on 11/5/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/2/2023 APPLICANT
Assigned to Plan Check Engineer 5/18/2023 SERGIO GUTIERREZ
Corrections Issued 5/23/2023 SERGIO GUTIERREZ
Quality Review Completed 5/31/2023 RODOLFO ARIAS
Applicant returned to address corrections 9/5/2023 SERGIO GUTIERREZ
Applicant returned to address corrections 11/1/2023 SERGIO GUTIERREZ
Plan Check Approved 2/2/2024 SERGIO GUTIERREZ
Issued 2/6/2024 APPLICANT
CofO in Progress 11/1/2024 ALIZAH MAYAGOITIA
CofO Issued 11/5/2024 RUBEN SALAS
Permit Finaled 11/5/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/7/2023 WALLIE JONG
Roof/Waste drainage to street Cleared 6/7/2023 WALLIE JONG
Sewer availability Cleared 6/7/2023 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 6/14/2023 WALLIE JONG
Hydrant and Access approval Cleared 8/11/2023 JOHN CONNEALLY
Hold Cleared 4/30/2024 MARIA VENDIVIL

Contact Information

Contractor Owner-Builder       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/1/2024 Corrections Issued ALIZAH MAYAGOITIA
PLUMBING-Rough 5/6/2024 Corrections Issued ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 5/7/2024 Corrections Issued ALIZAH MAYAGOITIA
PLUMBING-Rough 5/7/2024 Partial Approval ALIZAH MAYAGOITIA
Footing/Foundation/Slab 5/10/2024 Corrections Issued ALIZAH MAYAGOITIA
PLUMBING-Rough 5/10/2024 Partial Approval ALIZAH MAYAGOITIA
Footing/Foundation/Slab 5/13/2024 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Rough 5/29/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
Interior/Exterior Lathing 5/29/2024 Partial Approval ALIZAH MAYAGOITIA
PLUMBING-Rough 5/29/2024 Corrections Issued ALIZAH MAYAGOITIA
Underground Mechanical 5/29/2024 Corrections Issued ALIZAH MAYAGOITIA
PLUMBING-Rough 5/31/2024 Not Ready for Inspection OSVALDO PARAMO
Shower Pan 6/17/2024 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Rough 7/8/2024 Corrections Issued ALIZAH MAYAGOITIA
PLUMBING-Rough 7/8/2024 Corrections Issued ALIZAH MAYAGOITIA
ELECTRICAL-Rough 7/29/2024 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 8/8/2024 Approved ALIZAH MAYAGOITIA
Insulation 8/8/2024 Approved ALIZAH MAYAGOITIA
PLUMBING-Rough 8/8/2024 Approved ALIZAH MAYAGOITIA
Drywall Nailing 8/12/2024 Approved ALIZAH MAYAGOITIA
HVAC-Final 9/10/2024 Approved ALIZAH MAYAGOITIA
PLUMBING-Final 9/10/2024 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 9/25/2024 Approved ALIZAH MAYAGOITIA
Final 9/25/2024 Corrections Issued ALIZAH MAYAGOITIA
Green Building Final 9/25/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
Green Building Rough 9/25/2024 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 9/25/2024 SGSOV Approved ALIZAH MAYAGOITIA
Smoke Detectors 9/25/2024 Approved ALIZAH MAYAGOITIA
Final 10/21/2024 Partial Approval ALIZAH MAYAGOITIA
Green Building Final 10/21/2024 Approved ALIZAH MAYAGOITIA
Final 11/1/2024 OK to Issue CofO ALIZAH MAYAGOITIA