8424 S TRUXTON AVE 90045
Certificate Information: 8424 S TRUXTON AVE 90045
- Application / Permit
- 23016-10000-16804
- Plan Check / Job No.
- B23LA09558
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Remodel in the rear of (E) SFD creating a new bedroom. Demo portion of (E) flat roof to make a vaulted ceiling in the rear of (E) SFD. No change in building dimensions or overall height. All work done per engineering.
- Permit Issued
- Issued on 6/8/2023
- Issuing Office
- West Los Angeles
- Current Status
- Permit Finaled on 1/5/2024
Permit Application Status History
| Submitted | 5/23/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/23/2023 | WEIJIAN HUANG |
| Corrections Issued | 5/23/2023 | WEIJIAN HUANG |
| Plan Check Approved | 5/31/2023 | DANIEL SMILEY |
| Issued | 6/8/2023 | APPLICANT |
| Permit Finaled | 1/5/2024 | BOBBY KEY |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/30/2023 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 5/30/2023 | ANTHONY MAINEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/11/2023 | Corrections Issued | JESUS PINEDA |
| ELECTRICAL-Rough | 8/22/2023 | Approved | BOBBY KEY |
| Footing/Foundation/Slab | 8/22/2023 | Not Ready for Inspection | BOBBY KEY |
| HVAC-Rough | 8/22/2023 | Not Ready for Inspection | BOBBY KEY |
| PLUMBING-Rough | 8/22/2023 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 8/25/2023 | Corrections Issued | BOBBY KEY |
| Footing/Foundation/Slab | 8/25/2023 | Approved | BOBBY KEY |
| HVAC-Rough | 8/25/2023 | Approved | BOBBY KEY |
| PLUMBING-Rough | 8/25/2023 | Corrections Issued | BOBBY KEY |
| BUILDING-Rough-Frame | 9/11/2023 | Not Ready for Inspection | RICHARD STEINBACH |
| Floor/Roof Diaphrgm/Shear Wall | 9/11/2023 | Partial Approval | RICHARD STEINBACH |
| Gas Test | 9/11/2023 | Partial Approval | RICHARD STEINBACH |
| PLUMBING-Rough | 9/11/2023 | Conditional Approval | RICHARD STEINBACH |
| BUILDING-Rough-Frame | 9/18/2023 | Approved | BOBBY KEY |
| Gas Test | 9/18/2023 | Corrections Issued | BOBBY KEY |
| Interior/Exterior Lathing | 9/18/2023 | Approved | BOBBY KEY |
| Shower Pan | 9/18/2023 | Approved | BOBBY KEY |
| Insulation | 9/19/2023 | Approved | RICHARD STEINBACH |
| Drywall Nailing | 9/26/2023 | Approved | BOBBY KEY |
| Gas Test | 9/26/2023 | Approved | BOBBY KEY |
| PLUMBING-Rough | 9/26/2023 | Approved | BOBBY KEY |
| Final | 1/5/2024 | Permit Finaled | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 1/5/2024 | SGSOV Approved | BOBBY KEY |
| Smoke Detectors | 1/5/2024 | Approved | BOBBY KEY |