2999 W 6TH ST #104 90020
Certificate Information: 2999 W 6TH ST #104 90020
- Application / Permit
- 23016-10000-16741
- Plan Check / Job No.
- B23LA09504
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- REMOVE (E) PATIO AND REPLACE W/ NEW PATIO FOR OUTDOOR DINING FOR (E) RESTAURANT
- Permit Issued
- Issued on 4/28/2025
- Issuing Office
- Metro
- Current Status
- Issued on 4/28/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/22/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/8/2023 | JOE VO |
| Corrections Issued | 6/26/2023 | JOE VO |
| Quality Review Completed | 6/27/2023 | KEN GILL |
| Building Plans Picked Up | 7/5/2023 | APPLICANT |
| Plan Check Approved | 4/28/2025 | JOE VO |
| Issued | 4/28/2025 | APPLICANT |
| CofO in Progress | 2/9/2026 | RONALD JIMENEZ |
| CofO Issued-Status Void | 2/13/2026 | ERNESTO CORRAL |
| Permit Finaled-Status Void | 2/13/2026 | ERNESTO CORRAL |
| Re-Activate Permit | 3/18/2026 | ERNESTO CORRAL |
Permit Application Clearance Information
| "Q" conditions | Cleared | 9/15/2023 | SPENCER WEJROWSKI |
| "T" removal | Cleared | 9/15/2023 | SPENCER WEJROWSKI |
| CPC | Cleared | 9/15/2023 | SPENCER WEJROWSKI |
| ZA Case | Cleared | 3/28/2024 | MATTHEW COMPANA |
| Grading Pre-Inspection | Cleared | 5/24/2024 | LANNY MERRICK |
| Food Service Establishment | Cleared | 11/14/2024 | PAWAN VERMA |
| Fire Marshal Fire Life Safety | Cleared | 3/7/2025 | FIRE DEPARTMENT |
| DAS Clearance | Cleared | 3/25/2025 | JOE VO |
| Food establishment approval | Cleared | 3/27/2025 | LACDHS APPROVED |
| Miscellaneous | Cleared | 3/27/2025 | JOE VO |
| Eng Process Fee Ord 176,300 | Cleared | 3/29/2025 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 3/29/2025 | ADRIAN SANCHEZ |
Contact Information
| Contractor | Elden Development Construction Inc; Lic. No.: 970717-B | 440 S SHATTO PL SUITE 317 LOS ANGELES, CA 90020 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/9/2025 | Partial Approval | JEROME BLACKWOOD |
| Deputy Steel/Welding | 5/30/2025 | No Result Entered | |
| Footing/Foundation/Slab | 6/3/2025 | Partial Approval | LUIS CCAMACHO |
| Structural Steel Frame | 6/3/2025 | Not Ready for Inspection | LUIS CCAMACHO |
| Footing/Foundation/Slab | 8/12/2025 | Approved | EDWIN GREGORYONA |
| Floor/Roof Diaphrgm/Shear Wall | 8/26/2025 | Partial Approval | JEROME BLACKWOOD |
| Drywall Nailing | 9/22/2025 | Not Ready for Inspection | TIMOTHY POWELL |
| Final | 2/4/2026 | OK to Issue CofO | RONALD JIMENEZ |
| METHANE-Final | 2/4/2026 | Approved | RONALD JIMENEZ |
| SGSOV-Seismic Gas S/O Valve | 2/4/2026 | SGSOV Approved | RONALD JIMENEZ |
| Smoke Detectors | 2/4/2026 | Approved | RONALD JIMENEZ |