2999 W 6TH ST #104 90020

Certificate Information: 2999 W 6TH ST #104 90020

Application / Permit
23016-10000-16741
Plan Check / Job No.
B23LA09504
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(17) Restaurant
Work Description
REMOVE (E) PATIO AND REPLACE W/ NEW PATIO FOR OUTDOOR DINING FOR (E) RESTAURANT
Permit Issued
Issued on 4/28/2025
Issuing Office
Metro
Current Status
Issued on 4/28/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/22/2023 APPLICANT
Assigned to Plan Check Engineer 6/8/2023 JOE VO
Corrections Issued 6/26/2023 JOE VO
Quality Review Completed 6/27/2023 KEN GILL
Building Plans Picked Up 7/5/2023 APPLICANT
Plan Check Approved 4/28/2025 JOE VO
Issued 4/28/2025 APPLICANT
CofO in Progress 2/9/2026 RONALD JIMENEZ
CofO Issued-Status Void 2/13/2026 ERNESTO CORRAL
Permit Finaled-Status Void 2/13/2026 ERNESTO CORRAL
Re-Activate Permit 3/18/2026 ERNESTO CORRAL

Permit Application Clearance Information

"Q" conditions Cleared 9/15/2023 SPENCER WEJROWSKI
"T" removal Cleared 9/15/2023 SPENCER WEJROWSKI
CPC Cleared 9/15/2023 SPENCER WEJROWSKI
ZA Case Cleared 3/28/2024 MATTHEW COMPANA
Grading Pre-Inspection Cleared 5/24/2024 LANNY MERRICK
Food Service Establishment Cleared 11/14/2024 PAWAN VERMA
Fire Marshal Fire Life Safety Cleared 3/7/2025 FIRE DEPARTMENT
DAS Clearance Cleared 3/25/2025 JOE VO
Food establishment approval Cleared 3/27/2025 LACDHS APPROVED
Miscellaneous Cleared 3/27/2025 JOE VO
Eng Process Fee Ord 176,300 Cleared 3/29/2025 ADRIAN SANCHEZ
Sewer availability Cleared 3/29/2025 ADRIAN SANCHEZ

Contact Information

Contractor Elden Development Construction Inc; Lic. No.: 970717-B 440 S SHATTO PL   SUITE 317    LOS ANGELES, CA 90020

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/9/2025 Partial Approval JEROME BLACKWOOD
Deputy Steel/Welding 5/30/2025 No Result Entered
Footing/Foundation/Slab 6/3/2025 Partial Approval LUIS CCAMACHO
Structural Steel Frame 6/3/2025 Not Ready for Inspection LUIS CCAMACHO
Footing/Foundation/Slab 8/12/2025 Approved EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 8/26/2025 Partial Approval JEROME BLACKWOOD
Drywall Nailing 9/22/2025 Not Ready for Inspection TIMOTHY POWELL
Final 2/4/2026 OK to Issue CofO RONALD JIMENEZ
METHANE-Final 2/4/2026 Approved RONALD JIMENEZ
SGSOV-Seismic Gas S/O Valve 2/4/2026 SGSOV Approved RONALD JIMENEZ
Smoke Detectors 2/4/2026 Approved RONALD JIMENEZ