1100 S GLENDON AVE Suite 100 90024
Certificate Information: 1100 S GLENDON AVE Suite 100 90024
- Application / Permit
- 23016-10000-16592
- Plan Check / Job No.
- B23LA09423
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- EPLAN *** PREPOSED ALTERATION TO (E) RESTAURANT; NO CHANGES IN USE OR OCCUPANCY
- Permit Issued
- Issued on 8/6/2024
- Issuing Office
- Current Status
- Issued on 8/6/2024
Permit Application Status History
| Submitted | 5/22/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/25/2023 | SINA KHOSRAVI |
| Corrections Issued | 5/30/2023 | SINA KHOSRAVI |
| Quality Review Completed | 6/2/2023 | GARO TELMI |
| Applicant returned to address corrections | 7/24/2023 | SINA KHOSRAVI |
| Applicant returned to address corrections | 9/18/2023 | SINA KHOSRAVI |
| Plan Check Approved | 11/29/2023 | SINA KHOSRAVI |
| Issued | 8/6/2024 | APPLICANT |
Permit Application Clearance Information
| Fire Marshal Fire Life Safety | Cleared | 6/3/2023 | MENOA AGHAJANI |
| Eng Process Fee Ord 176,300 | Cleared | 6/9/2023 | DINAH GARIN |
| Sewer availability | Cleared | 6/9/2023 | DINAH GARIN |
| ZA Case | Cleared | 6/9/2023 | YINGSHI HUANG |
| ZA Case | Cleared | 6/9/2023 | YINGSHI HUANG |
| ZA Case | Cleared | 6/9/2023 | YINGSHI HUANG |
| ZA Case | Cleared | 6/9/2023 | YINGSHI HUANG |
| ZA Case | Cleared | 6/9/2023 | YINGSHI HUANG |
| Specific Plan | Cleared | 6/13/2023 | KEVIN FULTON |
| ZI | Cleared | 6/13/2023 | KEVIN FULTON |
| ZI | Cleared | 6/13/2023 | KEVIN FULTON |
| ZA Case | Cleared | 6/21/2023 | EDWIN CANO |
| Green Code | Cleared | 7/21/2023 | Sarkis Harabedian |
| DAS Clearance | Cleared | 8/21/2023 | Sarkis Harabedian |
| Food establishment approval | Cleared | 11/29/2023 | LACDHS APPROVED |
| ZA Case | Cleared | 4/2/2024 | JASON CHAN |
Contact Information
| Architect | Lim,, Geoffrey Buenavista; Lic. No.: NA33396 | , |
| Contractor | Ebs Construction Services Inc; Lic. No.: 973962-B | , |
| Contractor | Empire Construction; Lic. No.: 973962-B | , |
| Engineer | Allen,, Thomas Christopher; Lic. No.: S5460 | 2 VENTURE, SUITE 200 IRVINE, CA 92618 |
Inspector Information
| ROGELIO REYNA, (310) 914-3920 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/8/2024 | Approved | MICHAEL PETRUSKO |
| Deputy Drilled-In Anchors | 11/7/2024 | Conditional Approval | MICHAEL PETRUSKO |
| Footing/Foundation/Slab | 11/13/2024 | Approved | MICHAEL PETRUSKO |
| Light Gage Steel Frame | 11/13/2024 | Approved | MICHAEL PETRUSKO |
| Deputy Drilled-In Anchors | 11/27/2024 | Conditional Approval | RICARDO ROBLES |
| Deputy Reinf. Concrete | 11/27/2024 | Conditional Approval | RICARDO ROBLES |
| Footing/Foundation/Slab | 12/5/2024 | Partial Approval | PAUL DAVIDSON |
| Light Gage Steel Frame | 1/21/2025 | Not Ready for Inspection | AMANUEL BERHE |
| Light Gage Steel Frame | 1/22/2025 | Partial Inspection | AMANUEL BERHE |
| Drywall Nailing | 1/24/2025 | Partial Inspection | AMANUEL BERHE |
| Insulation | 1/28/2025 | Approved | AMANUEL BERHE |
| Drywall Nailing | 2/3/2025 | Partial Approval | CASIMIR BRITTON |
| Structural Steel Frame | 2/3/2025 | Partial Approval | CASIMIR BRITTON |
| Light Gage Steel Frame | 2/12/2025 | Partial Approval | PAUL DAVIDSON |
| Drywall Nailing | 2/21/2025 | Partial Approval | RICARDO ROBLES |
| Drywall Nailing | 2/24/2025 | Not Ready for Inspection | RICARDO ROBLES |
| Light Gage Steel Frame | 3/15/2025 | Partial Approval | RICARDO ROBLES |
| Drywall Nailing | 3/17/2025 | Partial Inspection | AMANUEL BERHE |
| Light Gage Steel Frame | 3/18/2025 | Approved | PAUL DAVIDSON |
| Drywall Nailing | 3/20/2025 | Partial Approval | GRANT WOODS |
| T-Bar Ceiling | 3/20/2025 | Not Ready for Inspection | GRANT WOODS |
| Drywall Nailing | 3/22/2025 | Off-Hour Fees Due | |
| T-Bar Ceiling | 3/22/2025 | Off-Hour Fees Due | |
| T-Bar Ceiling | 3/24/2025 | Corrections Issued | CASIMIR BRITTON |
| T-Bar Ceiling | 3/29/2025 | Conditional Approval | RICARDO ROBLES |
| Final | 4/17/2025 | Not Ready for Inspection | RICARDO ROBLES |
| Green Building Final | 4/17/2025 | Approved | RICARDO ROBLES |
| SGSOV-Seismic Gas S/O Valve | 4/17/2025 | SGSOV Approved | RICARDO ROBLES |
| Smoke Detectors | 4/17/2025 | Approved | RICARDO ROBLES |
| Special/Order Compliance | 4/18/2025 | Partial Inspection | RICARDO ROBLES |