10840 W NATIONAL BLVD 90064
Certificate Information: 10840 W NATIONAL BLVD 90064
- Application / Permit
- 23016-10000-16514
- Plan Check / Job No.
- B23LA09417
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Pharmacy prescription
- Work Description
- EPLAN CHANGE OF USE FROM BANK TO PHARMACY AND INTERIOR REMODEL.
- Permit Issued
- Issued on 8/9/2023
- Issuing Office
- Current Status
- CofO Issued on 9/13/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/22/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/26/2023 | MOHAMMAD ESMAILI |
| Corrections Issued | 5/30/2023 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 6/9/2023 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 6/16/2023 | PINANK PATEL |
| Applicant returned to address corrections | 6/16/2023 | JOE VO |
| Plan Check Approved | 8/9/2023 | DANIEL YIP |
| Issued | 8/9/2023 | APPLICANT |
| CofO in Progress | 9/11/2023 | FARHAD DADBIN |
| Permit Finaled | 9/13/2023 | DAVID TSAU |
| CofO Issued | 9/13/2023 | DAVID TSAU |
| Permit Finaled | 9/13/2023 | DAVID TSAU |
Permit Application Clearance Information
| ZA Case | Cleared | 6/20/2023 | RUBEN VASQUEZ |
| ZA Case | Cleared | 6/20/2023 | RUBEN VASQUEZ |
| ZA Case | Cleared | 6/20/2023 | RUBEN VASQUEZ |
| ZA Case | Cleared | 6/20/2023 | RUBEN VASQUEZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/21/2023 | AHMED AMARRAGY |
| Sewer availability | Cleared | 6/21/2023 | AHMED AMARRAGY |
| Specific Plan | Cleared | 7/5/2023 | JULISSA LOPEZ-HODOYAN |
| Comm Cor/Mini-Mall | Cleared | 7/11/2023 | YINGSHI HUANG |
| Specific Plan | Cleared | 7/31/2023 | PEDRO AYALA |
Contact Information
| Contractor | Coastline Development Inc; Lic. No.: 485187-B | , |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 8/16/2023 | Approved | AMANUEL BERHE |
| Drywall Nailing | 8/18/2023 | Approved | FARHAD DADBIN |
| Final | 9/6/2023 | OK to Issue CofO | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 9/6/2023 | SGSOV No Gas | FARHAD DADBIN |
| Smoke Detectors | 9/6/2023 | Approved | FARHAD DADBIN |