5248 E HUNTINGTON DR SOUT 90032

Certificate Information: 5248 E HUNTINGTON DR SOUT 90032

Application / Permit
23016-10000-16354
Plan Check / Job No.
B23LA09371
Group
Building
Type
Bldg-Addition
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
eplan 1-story Office & Parking Garage addition to existing 1-story Office building & Tenant Improvement. New exterior walls, new structural columns and beams, new concrete topping slab finish floor, new interior walls
Permit Issued
Issued on 1/22/2025
Issuing Office
Current Status
CofO Issued on 2/12/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/19/2023 APPLICANT
Assigned to Plan Check Engineer 5/25/2023 PRANITA SHAH
Corrections Issued 6/13/2023 PRANITA SHAH
Quality Review Completed 6/13/2023 GARO TELMI
Applicant returned to address corrections 8/1/2023 PRANITA SHAH
Applicant returned to address corrections 2/8/2024 PRANITA SHAH
Applicant returned to address corrections 6/12/2024 PRANITA SHAH
Applicant returned to address corrections 6/27/2024 PRANITA SHAH
Plan Check Approved 1/21/2025 PRANITA SHAH
Issued 1/22/2025 APPLICANT
CofO in Progress 2/11/2026 RONALD JIMENEZ
Permit Finaled 2/12/2026 RAFAEL ESPINOZA
CofO Issued 2/12/2026 RAFAEL ESPINOZA
Permit Finaled 2/12/2026 RAFAEL ESPINOZA

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/12/2023 ARNULFO CHAMU
Sewer availability Cleared 12/12/2023 ARNULFO CHAMU
"Q" conditions Cleared 12/20/2023 MATHEW QUAN
DAS Clearance Cleared 9/17/2024 Rosendo Medina
Green Code Cleared 1/3/2025 Rosendo Medina

Contact Information

Contractor Owner-Builder       ,
Engineer Dominguez,, Refugio; Lic. No.: C50820 254 COTTONWOOD ST      ONTARIO, CA 91761

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/11/2025 Approved RONALD JIMENEZ
Special/Order Compliance 2/11/2025 Corrections Issued RONALD JIMENEZ
Footing/Foundation/Slab 4/22/2025 Approved RONALD JIMENEZ
Floor/Roof Diaphrgm/Shear Wall 5/23/2025 Partial Approval PAUL BAZERKANIAN
Interior/Exterior Lathing 5/30/2025 Partial Approval PAUL BAZERKANIAN
Insulation 7/10/2025 Approved RONALD JIMENEZ
Floor/Roof Diaphrgm/Shear Wall 7/17/2025 Not Ready for Inspection RONALD JIMENEZ
Green Building Rough 7/17/2025 Approved RONALD JIMENEZ
Drywall Nailing 7/23/2025 Approved RONALD JIMENEZ
Floor/Roof Diaphrgm/Shear Wall 7/23/2025 Approved RONALD JIMENEZ
Wood Frame 7/23/2025 Approved RONALD JIMENEZ
Pre-Inspection 9/5/2025 Approved RONALD JIMENEZ
Final 9/9/2025 Not Ready for Inspection JEROME BLACKWOOD
Green Building Final 9/9/2025 Not Ready for Inspection JEROME BLACKWOOD
SGSOV-Seismic Gas S/O Valve 9/9/2025 SGSOV Not Ready JEROME BLACKWOOD
Smoke Detectors 9/9/2025 Not Ready for Inspection JEROME BLACKWOOD
Excavation/Setback/Form/Re-Bar 10/8/2025 Approved RONALD JIMENEZ
Final 1/15/2026 Not Ready for Inspection LARRY ARNICK
Green Building Final 1/15/2026 Approved LARRY ARNICK
SGSOV-Seismic Gas S/O Valve 1/15/2026 SGSOV Approved LARRY ARNICK
Smoke Detectors 1/15/2026 Approved LARRY ARNICK
Final 2/11/2026 OK to Issue CofO RONALD JIMENEZ