1651 N AVENUE 46 90041
Certificate Information: 1651 N AVENUE 46 90041
- Application / Permit
- 23016-10000-16330
- Plan Check / Job No.
- B23LA09360
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Convert (E) Duplex into SFD and major remodel to add bedrooms
- Permit Issued
- Issued on 3/11/2024
- Issuing Office
- Current Status
- CofO Issued on 2/7/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/30/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/1/2023 | HERNAN ARREOLA |
| Corrections Issued | 6/12/2023 | HERNAN ARREOLA |
| Quality Review Completed | 6/21/2023 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 7/20/2023 | HERNAN ARREOLA |
| Applicant returned to address corrections | 7/31/2023 | HERNAN ARREOLA |
| Applicant returned to address corrections | 12/18/2023 | HERNAN ARREOLA |
| Plan Check Approved | 12/19/2023 | HERNAN ARREOLA |
| Plan Check Approved | 3/4/2024 | HERNAN ARREOLA |
| Plan Check Approved | 3/8/2024 | INTERNET PERMIT |
| Issued | 3/11/2024 | APPLICANT |
| CofO in Progress | 2/4/2026 | DAVID WILLIAMS |
| Permit Finaled | 2/7/2026 | DEROLD HAUFF |
| CofO Issued | 2/7/2026 | DEROLD HAUFF |
| Permit Finaled | 2/7/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/18/2023 | JESSICA OPINION |
| Roof/Waste drainage to street | Cleared | 7/18/2023 | JESSICA OPINION |
| Eng Process Fee Ord 176,300 | Cleared | 7/19/2023 | JESSICA OPINION |
| Sewer availability | Cleared | 7/19/2023 | JESSICA OPINION |
| Tenant Habitability Plan | Cleared | 8/3/2023 | RICARDO BOHORQUEZ |
| Demo/Removal of Rental Units | Cleared | 12/1/2023 | SUSAN LIM |
Contact Information
| Contractor | Landmark Building & Design Inc; Lic. No.: 982610-B | , |
| Contractor | Level 42 Construction; Lic. No.: 982610-B | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/4/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 4/5/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 5/6/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 5/8/2024 | Conditional Approval | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 6/24/2024 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Rough | 6/24/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 6/24/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 7/11/2024 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Rough | 7/11/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 7/11/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 7/15/2024 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Rough | 7/15/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 7/15/2024 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 7/25/2024 | Partial Approval | CRAIG VAUGHAN |
| Green Building Rough | 7/25/2024 | Approved | CRAIG VAUGHAN |
| Verify Sprinkler Sign Off | 7/25/2024 | Approved | CRAIG VAUGHAN |
| Insulation | 8/12/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Insulation | 9/3/2024 | Partial Approval | LUIS CASTRO |
| Interior/Exterior Lathing | 9/5/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Drywall Nailing | 9/17/2024 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 10/1/2024 | Approved | ROY SPAULDING |
| Interior/Exterior Lathing | 10/21/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Service/Power Release | 4/1/2025 | Approved | DAVID WILLIAMS |
| Service/Power Release | 5/21/2025 | Approved | DAVID WILLIAMS |
| BUILDING-Rough-Frame | 9/24/2025 | Approved | DAVID WILLIAMS |
| Final | 9/24/2025 | Corrections Issued | DAVID WILLIAMS |
| Green Building Final | 9/24/2025 | Approved | DAVID WILLIAMS |
| SGSOV-Seismic Gas S/O Valve | 9/24/2025 | SGSOV No Gas | DAVID WILLIAMS |
| Smoke Detectors | 9/24/2025 | Approved | DAVID WILLIAMS |
| Final | 2/2/2026 | Not Ready for Inspection | DAVID WILLIAMS |
| Final | 2/4/2026 | OK to Issue CofO | DAVID WILLIAMS |