2029 S CENTURY PARK EAST 2900-2950N 90067

Certificate Information: 2029 S CENTURY PARK EAST 2900-2950N 90067

Application / Permit
23016-10000-16200
Plan Check / Job No.
B23LA09292
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
SCOPE OF WORK: OFFICE T.I. INCLUDING NEW NON-BEARING PARTITIONS, MILLWORK, CEILING, DOORS AND FRAMES, FIXTURES, CARPET, AND PAINT FINISHES. AREA OF WORK: 21,949 SF
Permit Issued
Issued on 6/27/2023
Issuing Office
Current Status
Permit Finaled on 3/6/2024

Permit Application Status History

Submitted 5/18/2023 APPLICANT
Assigned to Plan Check Engineer 5/22/2023 WEIJIAN HUANG
Corrections Issued 5/23/2023 WEIJIAN HUANG
Building Plans Picked Up 5/30/2023 APPLICANT
Plan Check Approved 6/26/2023 VICTOR CHEN
Issued 6/27/2023 APPLICANT
Permit Finaled 3/4/2024 RICARDO ROBLES

Permit Application Clearance Information

Fire Marshal Fire Life Safety Cleared 6/22/2023 FIRE DEPARTMENT

Contact Information

Contractor Clune Construction Company L P; Lic. No.: 732107-B 725 SOUTH FIGUEROA STREET   STE 300    LOS ANGELES, CA 90017

Inspector Information

ROGELIO REYNA, (310) 914-3920 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Light Gage Steel Frame 7/25/2023 Partial Approval PAUL DAVIDSON
Drywall Nailing 8/4/2023 Partial Approval PAUL DAVIDSON
Deputy Steel/Welding 8/14/2023 Conditional Approval PAUL DAVIDSON
Light Gage Steel Frame 8/15/2023 Approved MICHAEL PETRUSKO
Drywall Nailing 8/17/2023 Approved PAUL DAVIDSON
Light Gage Steel Frame 8/24/2023 Approved PAUL DAVIDSON
T-Bar Ceiling 9/1/2023 Partial Approval PAUL DAVIDSON
Light Gage Steel Frame 9/7/2023 Partial Approval PAUL DAVIDSON
T-Bar Ceiling 9/19/2023 Not Ready for Inspection PAUL DAVIDSON
T-Bar Ceiling 9/21/2023 Partial Approval PAUL DAVIDSON
Deputy Steel/Welding 10/6/2023 Conditional Approval PAUL DAVIDSON
Final 10/12/2023 Not Ready for Inspection PAUL DAVIDSON
Green Building Final 10/12/2023 Not Ready for Inspection PAUL DAVIDSON
Light Gage Steel Frame 10/12/2023 Partial Approval PAUL DAVIDSON
SGSOV-Seismic Gas S/O Valve 10/12/2023 SGSOV Not Ready PAUL DAVIDSON
Smoke Detectors 10/12/2023 Not Ready for Inspection PAUL DAVIDSON
Special/Order Compliance 10/12/2023 Partial Inspection CASIMIR BRITTON
Light Gage Steel Frame 10/19/2023 Approved PAUL DAVIDSON
Drywall Nailing 10/27/2023 Partial Approval PAUL DAVIDSON
Drywall Nailing 11/2/2023 Approved PAUL DAVIDSON
T-Bar Ceiling 12/19/2023 Approved PAUL DAVIDSON
Final 3/4/2024 Permit Finaled RICARDO ROBLES
Green Building Final 3/4/2024 Approved RICARDO ROBLES
SGSOV-Seismic Gas S/O Valve 3/4/2024 SGSOV Approved RICARDO ROBLES
Smoke Detectors 3/4/2024 Approved RICARDO ROBLES