1771 W BLAKE AVE Building 1 90031

Certificate Information: 1771 W BLAKE AVE Building 1 90031

Application / Permit
23016-10000-16154
Plan Check / Job No.
B23LA09263
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(23) Recreation Room
Work Description
ePlan TI to existing office building to include demo of existing non-bearing walls and new community room. New partitions, doors, ceilings, and restrooms. Structural work to include addition of metal stud walls at interior and exterior locations. (Building 1)
Permit Issued
Issued on 7/12/2024
Issuing Office
Current Status
CofO Issued on 3/13/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/18/2023 APPLICANT
Assigned to Plan Check Engineer 5/18/2023 FARSHAD ALIMOHAMADI
Corrections Issued 5/22/2023 FARSHAD ALIMOHAMADI
Quality Review Completed 6/13/2023 CHAD DOI
Applicant returned to address corrections 9/2/2023 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 4/26/2024 FARSHAD ALIMOHAMADI
Plan Check Approved 7/10/2024 FARSHAD ALIMOHAMADI
Issued 7/12/2024 APPLICANT
CofO in Progress 3/9/2026 RONALD JIMENEZ
Permit Finaled 3/13/2026 ERNESTO CORRAL
CofO Issued 3/13/2026 ERNESTO CORRAL
Permit Finaled 3/13/2026 ERNESTO CORRAL

Permit Application Clearance Information

"Q" conditions Cleared 9/8/2023 JASON CHAN
Miscellaneous Cleared 9/8/2023 JASON CHAN
Tract Map conditions Cleared 9/8/2023 JASON CHAN
ZI Cleared 9/8/2023 JASON CHAN
DAS Clearance Cleared 11/27/2023 Charles Chang

Contact Information

Architect Cunningham,, Gary Lynn; Lic. No.: C29285 18162 LILLIAN WAY      TUSTIN, CA 92780
Contractor Forza Construction Inc; Lic. No.: 914162-B 25243 AVENUE TIBBITS      VALENCIA, CA 91355
Engineer Burica,, Michael Jerome; Lic. No.: C57151 9283 RESEARCH DR      IRVINE, CA 92618

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/18/2024 Conditional Approval RAMAZANALI ALMASI
Footing/Foundation/Slab 12/18/2024 Partial Approval RAMAZANALI ALMASI
Interior/Exterior Lathing 8/8/2025 Not Ready for Inspection RONALD JIMENEZ
Light Gage Steel Frame 8/8/2025 Partial Approval RONALD JIMENEZ
Insulation 8/15/2025 Partial Approval RAFAEL CORTES
Interior/Exterior Lathing 8/15/2025 Not Ready for Inspection RAFAEL CORTES
Light Gage Steel Frame 8/15/2025 Partial Approval RAFAEL CORTES
Drywall Nailing 8/29/2025 Partial Approval RONALD JIMENEZ
Pre-Inspection 1/7/2026 Partial Approval RAFAEL CORTES
Pre-Inspection 2/5/2026 Approved RAFAEL CORTES
Final 2/10/2026 Corrections Issued RONALD JIMENEZ
Reinforced Masonry Frame 2/10/2026 Approved RONALD JIMENEZ
SGSOV-Seismic Gas S/O Valve 2/10/2026 SGSOV Approved RONALD JIMENEZ
Smoke Detectors 2/10/2026 Approved RONALD JIMENEZ
Final 2/27/2026 Partial Approval PAUL BAZERKANIAN
Final 3/9/2026 OK to Issue CofO RONALD JIMENEZ