832 N CRESCENT HEIGHTS BLVD 90046

Certificate Information: 832 N CRESCENT HEIGHTS BLVD 90046

Application / Permit
23016-10000-16144
Plan Check / Job No.
B23LA09262
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL TO EXISTING SINGLE FAMILY DWELLING AND REMOVAL OF EXISTING ATTACHED CARPORT - PER ENGINEER
Permit Issued
Issued on 7/7/2023
Issuing Office
Current Status
CofO Issued on 3/13/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/19/2023 APPLICANT
Assigned to Plan Check Engineer 5/24/2023 DANIEL ABRAMYAN
Corrections Issued 5/25/2023 DANIEL ABRAMYAN
Plan Check Approved 6/14/2023 DANIEL ABRAMYAN
Issued 7/7/2023 APPLICANT
CofO in Progress 3/10/2025 JOSE MACIAS
Permit Finaled 3/13/2025 DEROLD HAUFF
CofO Issued 3/13/2025 DEROLD HAUFF
Permit Finaled 3/13/2025 DEROLD HAUFF

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Bela Remodeling; Lic. No.: 1038287-B       ,
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22814 DOLOROSA ST      WOODLAND HILLS, CA 91367

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 8/30/2023 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Rough 10/13/2023 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 10/13/2023 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Rough 10/17/2023 Not Ready for Inspection JOSEPH MCGARRY
PLUMBING-Rough 10/17/2023 Not Ready for Inspection JOSEPH MCGARRY
ELECTRICAL-Rough 10/23/2023 Approved JOSEPH MCGARRY
PLUMBING-Rough 10/23/2023 Corrections Issued JOSEPH MCGARRY
BUILDING-Rough-Frame 10/26/2023 Not Ready for Inspection JOSEPH MCGARRY
PLUMBING-Rough 10/26/2023 Approved JOSEPH MCGARRY
HVAC-Rough 12/7/2023 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 12/11/2023 Approved LILIANA PORTILLO
Interior/Exterior Lathing 12/11/2023 Partial Approval LILIANA PORTILLO
Insulation 12/27/2023 Approved LILIANA PORTILLO
Drywall Nailing 1/9/2024 Approved BRENDAN MORELLI
Interior/Exterior Lathing 1/9/2024 Not Ready for Inspection BRENDAN MORELLI
Shower Pan 1/9/2024 Approved BRENDAN MORELLI
Interior/Exterior Lathing 1/12/2024 Approved LILIANA PORTILLO
Service/Power Release 1/12/2024 Approved LILIANA PORTILLO
ELECTRICAL-Final 8/16/2024 Corrections Issued AMIR NAZARIAN
Final 8/16/2024 Corrections Issued AMIR NAZARIAN
HVAC-Final 8/16/2024 Corrections Issued AMIR NAZARIAN
PLUMBING-Final 8/16/2024 Corrections Issued AMIR NAZARIAN
ELECTRICAL-Final 8/29/2024 Approved WILLIAM SIERRA
Final 8/29/2024 Partial Approval WILLIAM SIERRA
HVAC-Final 8/29/2024 Approved WILLIAM SIERRA
PLUMBING-Final 8/29/2024 Approved WILLIAM SIERRA
SGSOV-Seismic Gas S/O Valve 8/29/2024 SGSOV Approved WILLIAM SIERRA
Smoke Detectors 8/29/2024 Approved WILLIAM SIERRA
Final 9/4/2024 Corrections Issued JOSE MACIAS
Final 2/28/2025 OK to Issue CofO JOSE MACIAS