832 N CRESCENT HEIGHTS BLVD 90046
Certificate Information: 832 N CRESCENT HEIGHTS BLVD 90046
- Application / Permit
- 23016-10000-16144
- Plan Check / Job No.
- B23LA09262
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL TO EXISTING SINGLE FAMILY DWELLING AND REMOVAL OF EXISTING ATTACHED CARPORT - PER ENGINEER
- Permit Issued
- Issued on 7/7/2023
- Issuing Office
- Current Status
- CofO Issued on 3/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/19/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/24/2023 | DANIEL ABRAMYAN |
| Corrections Issued | 5/25/2023 | DANIEL ABRAMYAN |
| Plan Check Approved | 6/14/2023 | DANIEL ABRAMYAN |
| Issued | 7/7/2023 | APPLICANT |
| CofO in Progress | 3/10/2025 | JOSE MACIAS |
| Permit Finaled | 3/13/2025 | DEROLD HAUFF |
| CofO Issued | 3/13/2025 | DEROLD HAUFF |
| Permit Finaled | 3/13/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Bela Remodeling; Lic. No.: 1038287-B | , |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22814 DOLOROSA ST WOODLAND HILLS, CA 91367 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 8/30/2023 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Rough | 10/13/2023 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 10/13/2023 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Rough | 10/17/2023 | Not Ready for Inspection | JOSEPH MCGARRY |
| PLUMBING-Rough | 10/17/2023 | Not Ready for Inspection | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 10/23/2023 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 10/23/2023 | Corrections Issued | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 10/26/2023 | Not Ready for Inspection | JOSEPH MCGARRY |
| PLUMBING-Rough | 10/26/2023 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 12/7/2023 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 12/11/2023 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 12/11/2023 | Partial Approval | LILIANA PORTILLO |
| Insulation | 12/27/2023 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 1/9/2024 | Approved | BRENDAN MORELLI |
| Interior/Exterior Lathing | 1/9/2024 | Not Ready for Inspection | BRENDAN MORELLI |
| Shower Pan | 1/9/2024 | Approved | BRENDAN MORELLI |
| Interior/Exterior Lathing | 1/12/2024 | Approved | LILIANA PORTILLO |
| Service/Power Release | 1/12/2024 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 8/16/2024 | Corrections Issued | AMIR NAZARIAN |
| Final | 8/16/2024 | Corrections Issued | AMIR NAZARIAN |
| HVAC-Final | 8/16/2024 | Corrections Issued | AMIR NAZARIAN |
| PLUMBING-Final | 8/16/2024 | Corrections Issued | AMIR NAZARIAN |
| ELECTRICAL-Final | 8/29/2024 | Approved | WILLIAM SIERRA |
| Final | 8/29/2024 | Partial Approval | WILLIAM SIERRA |
| HVAC-Final | 8/29/2024 | Approved | WILLIAM SIERRA |
| PLUMBING-Final | 8/29/2024 | Approved | WILLIAM SIERRA |
| SGSOV-Seismic Gas S/O Valve | 8/29/2024 | SGSOV Approved | WILLIAM SIERRA |
| Smoke Detectors | 8/29/2024 | Approved | WILLIAM SIERRA |
| Final | 9/4/2024 | Corrections Issued | JOSE MACIAS |
| Final | 2/28/2025 | OK to Issue CofO | JOSE MACIAS |