3633 1/2 S EMPIRE DR 90034
Certificate Information: 3633 1/2 S EMPIRE DR 90034
- Application / Permit
- 23016-10000-16101
- Plan Check / Job No.
- B23LA09254
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- EPLAN: CONVERT EXISTING REC. ROOM, LAUNDRY AND PORTION OF EXISTING GARARE TO ADU AT TWO STORY APARTMRNT.
- Permit Issued
- Issued on 12/18/2023
- Issuing Office
- Current Status
- Issued on 12/18/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/22/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/25/2023 | TSE MING HUANG |
| Corrections Issued | 5/30/2023 | TSE MING HUANG |
| Quality Review Completed | 6/1/2023 | EUGENE BARBEAU |
| Plan Check Approved | 12/15/2023 | TSE MING HUANG |
| Issued | 12/18/2023 | APPLICANT |
Permit Application Clearance Information
| Specific Plan | Cleared | 6/13/2023 | JULISSA LOPEZ-HODOYAN |
| Tenant Habitability Plan | Cleared | 6/21/2023 | HUGO GARRIDO GARZA |
| Specific Plan | Cleared | 6/28/2023 | PEDRO AYALA |
| Sewer availability | Cleared | 7/27/2023 | WALLIE JONG |
| Address approval | Cleared | 8/7/2023 | ABEL CASILLAS |
| Eng Process Fee Ord 176,300 | Cleared | 8/29/2023 | WALLIE JONG |
| Construction near power lines | Cleared | 10/17/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 10/17/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 11 CEDARWOOD DR POMONA, CA 91766 |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/1/2024 | Conditional Approval | FARHAD DADBIN |
| Footing/Foundation/Slab | 2/2/2024 | Not Ready for Inspection | GRANT WOODS |
| Footing/Foundation/Slab | 2/13/2024 | Conditional Approval | FARHAD DADBIN |
| Wood Frame | 3/11/2024 | Partial Approval | FARHAD DADBIN |
| Wood Frame | 3/22/2024 | Partial Approval | RICARDO ROBLES |
| Wood Frame | 3/29/2024 | Partial Approval | FARHAD DADBIN |
| Insulation | 4/8/2024 | Approved | FARHAD DADBIN |
| Drywall Nailing | 4/15/2024 | Approved | MICHAEL PETRUSKO |
| Interior/Exterior Lathing | 4/15/2024 | Approved | MICHAEL PETRUSKO |
| Final | 7/9/2024 | Partial Approval | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 7/9/2024 | SGSOV Approved | FARHAD DADBIN |
| Smoke Detectors | 7/9/2024 | Approved | FARHAD DADBIN |
| Wood Frame | 7/9/2024 | Approved | FARHAD DADBIN |