2543 1/2 S VETERAN AVE 90064
Certificate Information: 2543 1/2 S VETERAN AVE 90064
- Application / Permit
- 23016-10000-16096
- Plan Check / Job No.
- B23LA09251
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan Convert existing DETACHED GARAGE into and accessory dwelling unit (ADU) PER STATE LAW
- Permit Issued
- Issued on 1/11/2024
- Issuing Office
- Current Status
- CofO Issued on 6/23/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/18/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/23/2023 | KHUONG TRUONG |
| Corrections Issued | 5/23/2023 | KHUONG TRUONG |
| Plan Check Approved | 9/9/2023 | KHUONG TRUONG |
| No Progress | 1/9/2024 | KHUONG TRUONG |
| Plan Check Approved | 1/9/2024 | KHUONG TRUONG |
| Issued | 1/11/2024 | APPLICANT |
| CofO in Progress | 6/21/2025 | MICHAEL PELHAM |
| Permit Finaled | 6/23/2025 | RICHARD STEINBACH |
| CofO Issued | 6/23/2025 | RICHARD STEINBACH |
| Permit Finaled | 6/23/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 7/19/2023 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 7/19/2023 | DARIN LAM |
| Sewer availability | Cleared | 7/19/2023 | DARIN LAM |
| Specific Plan | Cleared | 8/4/2023 | PEDRO AYALA |
| Construction near power lines | Cleared | 9/8/2023 | RIDWAN HARDY |
Contact Information
| Architect | , ; Lic. No.: C37075 | , |
| Contractor | Concept Renovations Inc; Lic. No.: 1016942-B | , |
| Engineer | Chang,, Yeh; Lic. No.: S6868 | 168 S SIERRA MADRE BLVD 109 PASADENA, CA 91107 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/26/2024 | Partial Inspection | JESUS PINEDA |
| PLUMBING-Rough | 2/26/2024 | Partial Approval | JESUS PINEDA |
| Sewer | 2/26/2024 | Approved | JESUS PINEDA |
| Underground Mechanical | 2/26/2024 | Approved | JESUS PINEDA |
| Footing/Foundation/Slab | 3/18/2024 | Corrections Issued | JESUS PINEDA |
| ELECTRICAL-Rough | 4/16/2024 | Approved | JESUS PINEDA |
| Footing/Foundation/Slab | 4/16/2024 | Approved | JESUS PINEDA |
| HVAC-Rough | 4/16/2024 | Approved | JESUS PINEDA |
| PLUMBING-Rough | 4/16/2024 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 4/25/2024 | Partial Approval | JESUS PINEDA |
| Green Building Rough | 4/25/2024 | Not Ready for Inspection | JESUS PINEDA |
| BUILDING-Rough-Frame | 4/30/2024 | Approved | JESUS PINEDA |
| Green Building Rough | 4/30/2024 | Approved | JESUS PINEDA |
| Insulation | 4/30/2024 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 4/30/2024 | Partial Approval | JESUS PINEDA |
| Drywall Nailing | 5/17/2024 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 6/4/2024 | Approved | JESUS PINEDA |
| Shower Pan | 6/4/2024 | Approved | JESUS PINEDA |
| Final | 7/11/2024 | Corrections Issued | JESUS PINEDA |
| Green Building Final | 7/11/2024 | Corrections Issued | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 7/11/2024 | SGSOV Approved | JESUS PINEDA |
| Smoke Detectors | 7/11/2024 | Approved | JESUS PINEDA |
| Final | 6/21/2025 | OK to Issue CofO | MICHAEL PELHAM |