400 S HOPE ST 90071

Certificate Information: 400 S HOPE ST 90071

Application / Permit
23016-10000-16039
Plan Check / Job No.
B23LA09215
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
ePlan FULL FLOOR TENANT IMPROVEMENT ON 18TH FLOOR; INCLUDES NEW OPENING IN FLOOR FOR SINK.
Permit Issued
Issued on 8/9/2023
Issuing Office
Current Status
Permit Finaled on 10/24/2024

Permit Application Status History

Submitted 5/23/2023 APPLICANT
Assigned to Plan Check Engineer 5/26/2023 SAMUEL GONZALEZ
Corrections Issued 5/27/2023 SAMUEL GONZALEZ
Plan Check Approved 8/4/2023 SAMUEL GONZALEZ
Issued 8/9/2023 APPLICANT
Permit Finaled 10/24/2024 LUIS CCAMACHO

Permit Application Clearance Information

Fire Marshal Fire Life Safety Cleared 8/2/2023 MENOA AGHAJANI

Contact Information

Architect , ; Lic. No.: C34719       ,
Contractor Howard Building Corporation; Lic. No.: 445804-B       ,
Engineer Lam,, Howard K; Lic. No.: S2717 32712 RACHEL CIRCLE      DANA POINT, CA 92629

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Light Gage Steel Frame 10/16/2023 Partial Inspection KATY RAMIREZ
Insulation 10/20/2023 Partial Approval KATY RAMIREZ
Deputy Steel/Welding 10/23/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 10/24/2023 Conditional Approval RAMAZANALI ALMASI
Drywall Nailing 10/24/2023 Partial Inspection JACOB MYERS
Light Gage Steel Frame 11/9/2023 Partial Approval JEROME BLACKWOOD
Drywall Nailing 12/4/2023 Partial Approval KATY RAMIREZ
Light Gage Steel Frame 1/3/2024 Partial Approval KATY RAMIREZ
Light Gage Steel Frame 1/4/2024 No Access for Inspection KATY RAMIREZ
Light Gage Steel Frame 1/12/2024 Partial Inspection KATY RAMIREZ
Structural Steel Frame 1/12/2024 Partial Inspection KATY RAMIREZ
T-Bar Ceiling 2/1/2024 Not Ready for Inspection KATY RAMIREZ
Insulation 2/2/2024 Approved KATY RAMIREZ
Light Gage Steel Frame 2/2/2024 Partial Approval KATY RAMIREZ
T-Bar Ceiling 2/2/2024 Partial Approval RICARDO ROBLES
Drywall Nailing 2/22/2024 Partial Approval KATY RAMIREZ
Light Gage Steel Frame 2/27/2024 Partial Approval LUIS CCAMACHO
Light Gage Steel Frame 3/1/2024 Partial Approval LUIS CCAMACHO
Light Gage Steel Frame 3/4/2024 No Access for Inspection RONALD JIMENEZ
Light Gage Steel Frame 3/7/2024 Not Ready for Inspection LUIS CCAMACHO
T-Bar Ceiling 3/7/2024 Not Ready for Inspection LUIS CCAMACHO
Light Gage Steel Frame 3/13/2024 Not Ready for Inspection LUIS CCAMACHO
T-Bar Ceiling 3/13/2024 Not Ready for Inspection LUIS CCAMACHO
Light Gage Steel Frame 3/15/2024 Not Ready for Inspection LUIS CCAMACHO
Light Gage Steel Frame 3/20/2024 Not Ready for Inspection LUIS CCAMACHO
Light Gage Steel Frame 3/22/2024 Partial Approval LUIS CCAMACHO
Light Gage Steel Frame 3/28/2024 Partial Approval LUIS CCAMACHO
Drywall Nailing 4/2/2024 Partial Approval LUIS CCAMACHO
Light Gage Steel Frame 4/3/2024 Partial Approval LUIS CCAMACHO
T-Bar Ceiling 4/3/2024 Not Ready for Inspection LUIS CCAMACHO
Drywall Nailing 4/8/2024 Partial Approval LUIS CCAMACHO
Light Gage Steel Frame 4/8/2024 Partial Approval LUIS CCAMACHO
T-Bar Ceiling 4/8/2024 Partial Approval LUIS CCAMACHO
Light Gage Steel Frame 4/10/2024 Not Ready for Inspection LUIS CCAMACHO
T-Bar Ceiling 4/10/2024 Not Ready for Inspection LUIS CCAMACHO
Drywall Nailing 4/15/2024 Partial Approval LUIS CCAMACHO
T-Bar Ceiling 4/22/2024 Partial Approval LUIS CCAMACHO
T-Bar Ceiling 4/26/2024 Partial Approval LUIS CCAMACHO
Interior/Exterior Lathing 5/10/2024 Partial Approval LUIS CCAMACHO
T-Bar Ceiling 5/10/2024 Partial Approval LUIS CCAMACHO
T-Bar Ceiling 5/22/2024 Not Ready for Inspection LUIS CCAMACHO
Final 5/24/2024 Not Ready for Inspection LUIS CCAMACHO
Green Building Final 5/24/2024 Not Ready for Inspection LUIS CCAMACHO
SGSOV-Seismic Gas S/O Valve 5/24/2024 SGSOV Not Ready LUIS CCAMACHO
Smoke Detectors 5/24/2024 Not Ready for Inspection LUIS CCAMACHO
Final 10/24/2024 Permit Finaled LUIS CCAMACHO
Green Building Final 10/24/2024 Approved LUIS CCAMACHO
SGSOV-Seismic Gas S/O Valve 10/24/2024 SGSOV Approved LUIS CCAMACHO
Smoke Detectors 10/24/2024 Approved LUIS CCAMACHO