400 S HOPE ST 90071

Certificate Information: 400 S HOPE ST 90071

Application / Permit
23016-10000-16038
Plan Check / Job No.
B23LA09213
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
ePlan - FULL FLOOR TENANT IMPROVEMENT ON 17TH FLOOR;
Permit Issued
Issued on 7/21/2023
Issuing Office
Current Status
Permit Finaled on 10/24/2024

Permit Application Status History

Submitted 5/23/2023 APPLICANT
Assigned to Plan Check Engineer 5/26/2023 MOHAMMAD ESMAILI
Corrections Issued 5/27/2023 MOHAMMAD ESMAILI
Plan Check Approved 7/20/2023 MOHAMMAD ESMAILI
Issued 7/21/2023 APPLICANT
Permit Finaled 10/24/2024 LUIS CCAMACHO

Permit Application Clearance Information

Fire Marshal Fire Life Safety Cleared 7/14/2023 ANDREW KO

Contact Information

Contractor Howard Building Corporation; Lic. No.: 445804-B       ,

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Light Gage Steel Frame 10/26/2023 Not Ready for Inspection RAMAZANALI ALMASI
Light Gage Steel Frame 10/30/2023 Partial Approval KATY RAMIREZ
Deputy Steel/Welding 10/31/2023 Conditional Approval KATY RAMIREZ
Insulation 10/31/2023 Partial Approval KATY RAMIREZ
T-Bar Ceiling 2/9/2024 Partial Approval KATY RAMIREZ
Light Gage Steel Frame 2/27/2024 Partial Approval LUIS CCAMACHO
Drywall Nailing 3/1/2024 Not Ready for Inspection LUIS CCAMACHO
Light Gage Steel Frame 3/1/2024 Not Ready for Inspection LUIS CCAMACHO
T-Bar Ceiling 3/1/2024 Not Ready for Inspection LUIS CCAMACHO
Light Gage Steel Frame 3/6/2024 Not Ready for Inspection LUIS CCAMACHO
Drywall Nailing 3/14/2024 Not Ready for Inspection LUIS CCAMACHO
T-Bar Ceiling 3/14/2024 Partial Approval LUIS CCAMACHO
Light Gage Steel Frame 3/27/2024 Partial Approval LUIS CCAMACHO
Drywall Nailing 4/8/2024 Partial Approval LUIS CCAMACHO
Light Gage Steel Frame 4/8/2024 Partial Approval LUIS CCAMACHO
T-Bar Ceiling 4/8/2024 Partial Approval LUIS CCAMACHO
Light Gage Steel Frame 4/10/2024 Not Ready for Inspection LUIS CCAMACHO
T-Bar Ceiling 4/10/2024 Not Ready for Inspection LUIS CCAMACHO
Drywall Nailing 4/15/2024 Partial Approval LUIS CCAMACHO
T-Bar Ceiling 4/22/2024 Partial Approval LUIS CCAMACHO
T-Bar Ceiling 4/26/2024 Partial Approval LUIS CCAMACHO
T-Bar Ceiling 5/10/2024 Partial Approval LUIS CCAMACHO
T-Bar Ceiling 5/22/2024 Not Ready for Inspection LUIS CCAMACHO
Final 5/24/2024 Not Ready for Inspection LUIS CCAMACHO
Green Building Final 5/24/2024 Not Ready for Inspection LUIS CCAMACHO
SGSOV-Seismic Gas S/O Valve 5/24/2024 SGSOV Not Ready LUIS CCAMACHO
Smoke Detectors 5/24/2024 Not Ready for Inspection LUIS CCAMACHO
Final 10/24/2024 Permit Finaled LUIS CCAMACHO
Green Building Final 10/24/2024 Approved LUIS CCAMACHO
SGSOV-Seismic Gas S/O Valve 10/24/2024 SGSOV Approved LUIS CCAMACHO
Smoke Detectors 10/24/2024 Approved LUIS CCAMACHO