400 S HOPE ST 90071

Certificate Information: 400 S HOPE ST 90071

Application / Permit
23016-10000-16017
Plan Check / Job No.
B23LA09201
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
ePlan FULL FLOOR TENANT IMPROVEMENT ON 16TH FLOOR; INCLUDES NEW FLOOR OPENING FOR SINK.
Permit Issued
Issued on 8/1/2023
Issuing Office
Current Status
Permit Finaled on 10/24/2024

Permit Application Status History

Submitted 5/23/2023 APPLICANT
Assigned to Plan Check Engineer 5/26/2023 PINANK PATEL
Corrections Issued 5/27/2023 PINANK PATEL
Plan Check Approved 7/14/2023 MICHAEL LOPEZ
Issued 8/1/2023 APPLICANT
Permit Finaled 10/24/2024 LUIS CCAMACHO

Permit Application Clearance Information

Fire Marshal Fire Life Safety Cleared 7/11/2023 MENOA AGHAJANI

Contact Information

Architect Alan, Thomas Young; Lic. No.: C34719       ,
Contractor Howard Building Corporation; Lic. No.: 445804-B       ,
Engineer Lam,, Howard K; Lic. No.: S2717 32712 RACHEL CIRCLE      DANA POINT, CA 92629

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Light Gage Steel Frame 11/1/2023 Partial Approval KATY RAMIREZ
Insulation 11/3/2023 Approved KATY RAMIREZ
T-Bar Ceiling 2/21/2024 No Access for Inspection KATY RAMIREZ
T-Bar Ceiling 2/22/2024 Partial Approval KATY RAMIREZ
Light Gage Steel Frame 3/1/2024 Not Ready for Inspection LUIS CCAMACHO
Light Gage Steel Frame 3/6/2024 Partial Approval LUIS CCAMACHO
Drywall Nailing 3/14/2024 Not Ready for Inspection LUIS CCAMACHO
T-Bar Ceiling 3/14/2024 Partial Approval LUIS CCAMACHO
Light Gage Steel Frame 3/27/2024 Partial Approval LUIS CCAMACHO
T-Bar Ceiling 4/3/2024 Not Ready for Inspection LUIS CCAMACHO
Drywall Nailing 4/8/2024 Not Ready for Inspection LUIS CCAMACHO
Light Gage Steel Frame 4/8/2024 Partial Approval LUIS CCAMACHO
T-Bar Ceiling 4/8/2024 Partial Approval LUIS CCAMACHO
Light Gage Steel Frame 4/10/2024 Partial Approval LUIS CCAMACHO
T-Bar Ceiling 4/10/2024 Partial Approval LUIS CCAMACHO
Drywall Nailing 4/15/2024 Partial Approval LUIS CCAMACHO
T-Bar Ceiling 4/22/2024 Partial Approval LUIS CCAMACHO
T-Bar Ceiling 4/26/2024 Partial Approval LUIS CCAMACHO
T-Bar Ceiling 5/10/2024 Partial Approval LUIS CCAMACHO
T-Bar Ceiling 5/22/2024 Not Ready for Inspection LUIS CCAMACHO
Final 5/24/2024 Not Ready for Inspection LUIS CCAMACHO
SGSOV-Seismic Gas S/O Valve 5/24/2024 SGSOV Not Ready LUIS CCAMACHO
Smoke Detectors 5/24/2024 Not Ready for Inspection LUIS CCAMACHO
Final 10/24/2024 Permit Finaled LUIS CCAMACHO
SGSOV-Seismic Gas S/O Valve 10/24/2024 SGSOV Approved LUIS CCAMACHO
Smoke Detectors 10/24/2024 Approved LUIS CCAMACHO