400 S HOPE ST 90071
Certificate Information: 400 S HOPE ST 90071
- Application / Permit
- 23016-10000-16017
- Plan Check / Job No.
- B23LA09201
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- ePlan FULL FLOOR TENANT IMPROVEMENT ON 16TH FLOOR; INCLUDES NEW FLOOR OPENING FOR SINK.
- Permit Issued
- Issued on 8/1/2023
- Issuing Office
- Current Status
- Permit Finaled on 10/24/2024
Permit Application Status History
| Submitted | 5/23/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/26/2023 | PINANK PATEL |
| Corrections Issued | 5/27/2023 | PINANK PATEL |
| Plan Check Approved | 7/14/2023 | MICHAEL LOPEZ |
| Issued | 8/1/2023 | APPLICANT |
| Permit Finaled | 10/24/2024 | LUIS CCAMACHO |
Permit Application Clearance Information
| Fire Marshal Fire Life Safety | Cleared | 7/11/2023 | MENOA AGHAJANI |
Contact Information
| Architect | Alan, Thomas Young; Lic. No.: C34719 | , |
| Contractor | Howard Building Corporation; Lic. No.: 445804-B | , |
| Engineer | Lam,, Howard K; Lic. No.: S2717 | 32712 RACHEL CIRCLE DANA POINT, CA 92629 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 11/1/2023 | Partial Approval | KATY RAMIREZ |
| Insulation | 11/3/2023 | Approved | KATY RAMIREZ |
| T-Bar Ceiling | 2/21/2024 | No Access for Inspection | KATY RAMIREZ |
| T-Bar Ceiling | 2/22/2024 | Partial Approval | KATY RAMIREZ |
| Light Gage Steel Frame | 3/1/2024 | Not Ready for Inspection | LUIS CCAMACHO |
| Light Gage Steel Frame | 3/6/2024 | Partial Approval | LUIS CCAMACHO |
| Drywall Nailing | 3/14/2024 | Not Ready for Inspection | LUIS CCAMACHO |
| T-Bar Ceiling | 3/14/2024 | Partial Approval | LUIS CCAMACHO |
| Light Gage Steel Frame | 3/27/2024 | Partial Approval | LUIS CCAMACHO |
| T-Bar Ceiling | 4/3/2024 | Not Ready for Inspection | LUIS CCAMACHO |
| Drywall Nailing | 4/8/2024 | Not Ready for Inspection | LUIS CCAMACHO |
| Light Gage Steel Frame | 4/8/2024 | Partial Approval | LUIS CCAMACHO |
| T-Bar Ceiling | 4/8/2024 | Partial Approval | LUIS CCAMACHO |
| Light Gage Steel Frame | 4/10/2024 | Partial Approval | LUIS CCAMACHO |
| T-Bar Ceiling | 4/10/2024 | Partial Approval | LUIS CCAMACHO |
| Drywall Nailing | 4/15/2024 | Partial Approval | LUIS CCAMACHO |
| T-Bar Ceiling | 4/22/2024 | Partial Approval | LUIS CCAMACHO |
| T-Bar Ceiling | 4/26/2024 | Partial Approval | LUIS CCAMACHO |
| T-Bar Ceiling | 5/10/2024 | Partial Approval | LUIS CCAMACHO |
| T-Bar Ceiling | 5/22/2024 | Not Ready for Inspection | LUIS CCAMACHO |
| Final | 5/24/2024 | Not Ready for Inspection | LUIS CCAMACHO |
| SGSOV-Seismic Gas S/O Valve | 5/24/2024 | SGSOV Not Ready | LUIS CCAMACHO |
| Smoke Detectors | 5/24/2024 | Not Ready for Inspection | LUIS CCAMACHO |
| Final | 10/24/2024 | Permit Finaled | LUIS CCAMACHO |
| SGSOV-Seismic Gas S/O Valve | 10/24/2024 | SGSOV Approved | LUIS CCAMACHO |
| Smoke Detectors | 10/24/2024 | Approved | LUIS CCAMACHO |