1150 S OLIVE ST 1800 90015
Certificate Information: 1150 S OLIVE ST 1800 90015
- Application / Permit
- 23016-10000-15921
- Plan Check / Job No.
- B23LA09126
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- eplan: Tenant Improvement to Include: Demolition, New non-structural partitions, suspended ceiling assemblies, lighting, doors, finishes, and associated electrical, mechanical, and plumbing improvements.
- Permit Issued
- Issued on 8/8/2023
- Issuing Office
- Current Status
- Permit Finaled on 4/17/2024
Permit Application Status History
| Submitted | 5/17/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/23/2023 | SAMUEL GONZALEZ |
| Corrections Issued | 5/24/2023 | SAMUEL GONZALEZ |
| Applicant returned to address corrections | 6/9/2023 | KEVIN MORALES |
| Plan Check Approved | 7/5/2023 | KEVIN MORALES |
| Issued | 8/8/2023 | APPLICANT |
| Permit Finaled | 4/17/2024 | LUIS CCAMACHO |
Permit Application Clearance Information
| Historic Resource Verification | Cleared | 6/9/2023 | CARTER HOWE |
| Redevelopment Project Area | Cleared | 6/9/2023 | CARTER HOWE |
| Fire Marshal Fire Life Safety | Cleared | 6/27/2023 | FIRE DEPARTMENT |
Contact Information
| Architect | Lindholm,, Christopher D; Lic. No.: C32504 | 17496 STAR CANYON COURT RIVERSIDE, CA 92503 |
| Contractor | D B A C Inc; Lic. No.: 637651-B | , |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Green Building Rough | 8/31/2023 | Approved | KATY RAMIREZ |
| Light Gage Steel Frame | 8/31/2023 | Partial Approval | KATY RAMIREZ |
| Insulation | 9/5/2023 | Approved | NICK DANERI |
| Drywall Nailing | 9/19/2023 | Partial Approval | KATY RAMIREZ |
| Light Gage Steel Frame | 10/2/2023 | Partial Approval | KATY RAMIREZ |
| Light Gage Steel Frame | 10/16/2023 | Partial Approval | KATY RAMIREZ |
| Drywall Nailing | 10/19/2023 | Approved | KATY RAMIREZ |
| T-Bar Ceiling | 10/19/2023 | Partial Inspection | KATY RAMIREZ |
| Final | 12/21/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| Green Building Final | 12/21/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| SGSOV-Seismic Gas S/O Valve | 12/21/2023 | SGSOV Approved | JEROME BLACKWOOD |
| Smoke Detectors | 12/21/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| Green Building Final | 12/29/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| Smoke Detectors | 12/29/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| Final | 4/16/2024 | Conditional Approval | LUIS CCAMACHO |
| Green Building Final | 4/16/2024 | Approved | LUIS CCAMACHO |
| SGSOV-Seismic Gas S/O Valve | 4/16/2024 | SGSOV Approved | LUIS CCAMACHO |
| Smoke Detectors | 4/16/2024 | Approved | LUIS CCAMACHO |
| Final | 4/17/2024 | Permit Finaled | LUIS CCAMACHO |