1943 N WILTON PL 90068
Certificate Information: 1943 N WILTON PL 90068
- Application / Permit
- 23016-10000-15906
- Plan Check / Job No.
- B23LA09112
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan KITCHEN, LAUNDRY, & POWDER ROOM REMODEL OF (E) SFD.
- Permit Issued
- Issued on 7/13/2023
- Issuing Office
- Current Status
- Permit Finaled on 10/23/2023
Permit Application Status History
| Submitted | 5/16/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/19/2023 | ALFREDO JARA |
| Corrections Issued | 5/21/2023 | ALFREDO JARA |
| Applicant returned to address corrections | 6/2/2023 | HANS SANTIAGO |
| Applicant returned to address corrections | 6/16/2023 | HANS SANTIAGO |
| Plan Check Approved | 7/12/2023 | ANDREW SANTIAGO |
| Issued | 7/13/2023 | APPLICANT |
| Permit Finaled | 10/20/2023 | STUART CHAPMAN |
Permit Application Clearance Information
| Historic Resource Verification | Cleared | 6/1/2023 | SUSAN WONG |
| HPOZ | Cleared | 6/8/2023 | MICAELA TORRES-GIL |
| Miscellaneous | Cleared | 6/8/2023 | MICAELA TORRES-GIL |
| ZI | Cleared | 6/8/2023 | MICAELA TORRES-GIL |
| Grading Pre-Inspection | Cleared | 7/12/2023 | ALFREDO JARA |
Contact Information
| Contractor | David'S Crew Inc; Lic. No.: 902629-B | , |
| Engineer | Ghanim,, Husam; Lic. No.: S5689 | 1594 CASITAS AVENUE PASADENA, CA 91103 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/19/2023 | Conditional Approval | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 7/19/2023 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 8/1/2023 | Approved | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 8/1/2023 | Approved | JOAQUIN GREENOUGH |
| HVAC-Rough | 8/1/2023 | Approved | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 8/1/2023 | Approved | JOAQUIN GREENOUGH |
| Insulation | 8/4/2023 | Approved | JOAQUIN GREENOUGH |
| Drywall Nailing | 8/9/2023 | Approved | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 10/2/2023 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 10/2/2023 | Partial Approval | JOAQUIN GREENOUGH |
| Final | 10/20/2023 | Permit Finaled | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 10/20/2023 | SGSOV Approved | STUART CHAPMAN |
| Smoke Detectors | 10/20/2023 | Approved | STUART CHAPMAN |