1301 N AMALFI DR 90272

Certificate Information: 1301 N AMALFI DR 90272

Application / Permit
23016-10000-15812
Plan Check / Job No.
B23LA09067
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan INTERIOR & EXTERIOR ALTERATION TO EXISTING 2 STORY SFD WITH BASEMENT. DEMOLISH AND FULLY EXTEND LOFT IN PORTION OF 1ST & 2ND FLOOR.
Permit Issued
Issued on 8/7/2023
Issuing Office
Current Status
Issued on 8/7/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/18/2023 APPLICANT
Assigned to Plan Check Engineer 6/1/2023 VIVIAN LAO
Corrections Issued 6/8/2023 VIVIAN LAO
Quality Review Completed 6/8/2023 GARO TELMI
Applicant returned to address corrections 7/11/2023 VIVIAN LAO
Plan Check Approved 7/12/2023 VIVIAN LAO
Issued 8/7/2023 APPLICANT

Permit Application Clearance Information

Grading Pre-Inspection Cleared 7/12/2023 VIVIAN LAO

Contact Information

Contractor Rumo Group Inc The; Lic. No.: 1043968-B       ,
Engineer Arutyunyan,, Vladimir; Lic. No.: C92714 3235 KIRKHAM DR      GLENDALE, CA 91206

Inspector Information

KEVIN SARGSYAN, (310) 914-3889 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/29/2023 Partial Inspection KEVIN SARGSYAN
PLUMBING-Rough 8/30/2024 Not Ready for Inspection KEVIN SARGSYAN
ELECTRICAL-Rough 9/5/2024 Approved EVAN COOPER
HVAC-Rough 9/5/2024 Corrections Issued EVAN COOPER
PLUMBING-Rough 9/5/2024 Approved EVAN COOPER
BUILDING-Rough-Frame 9/9/2024 Corrections Issued KEVIN SARGSYAN
BUILDING-Rough-Frame 9/13/2024 Corrections Issued JESUS RODRIGUEZ
HVAC-Rough 9/13/2024 Not Ready for Inspection JESUS RODRIGUEZ
BUILDING-Rough-Frame 9/16/2024 Approved KEVIN SARGSYAN
HVAC-Rough 9/16/2024 Approved KEVIN SARGSYAN
Insulation 9/16/2024 Approved KEVIN SARGSYAN
Drywall Nailing 10/7/2024 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 12/27/2024 Approved KEVIN SARGSYAN
Deputy Drilled-In Anchors 8/27/2025 Conditional Approval KEVIN SARGSYAN
ELECTRICAL-Rough 10/31/2025 Corrections Issued HERBERT GIRON
HVAC-Rough 10/31/2025 Corrections Issued HERBERT GIRON
ELECTRICAL-Rough 11/3/2025 Approved KEVIN SARGSYAN
HVAC-Rough 11/3/2025 Not Ready for Inspection KEVIN SARGSYAN
PLUMBING-Rough 11/3/2025 Corrections Issued KEVIN SARGSYAN
BUILDING-Rough-Frame 11/6/2025 Corrections Issued HERBERT GIRON
ELECTRICAL-Rough 11/6/2025 Approved HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 11/6/2025 Corrections Issued HERBERT GIRON
HVAC-Rough 11/6/2025 Approved HERBERT GIRON
PLUMBING-Rough 11/6/2025 Approved HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 11/10/2025 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 11/14/2025 Partial Approval MEL KHACHATOURIAN
BUILDING-Rough-Frame 11/17/2025 Approved KEVIN SARGSYAN
Insulation 11/21/2025 Corrections Issued HERBERT GIRON
Insulation 11/25/2025 Approved KEVIN SARGSYAN
Drywall Nailing 1/28/2026 Approved KEVIN SARGSYAN
Shower Pan 1/28/2026 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 2/2/2026 Approved STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 2/12/2026 Not Ready for Inspection HERBERT GIRON
PLUMBING-Rough 2/12/2026 Corrections Issued HERBERT GIRON
Wood Frame 2/12/2026 Not Ready for Inspection HERBERT GIRON
ELECTRICAL-Rough 2/20/2026 Corrections Issued KEVIN SARGSYAN
HVAC-Rough 2/23/2026 Approved KEVIN SARGSYAN
PLUMBING-Rough 2/23/2026 Corrections Issued KEVIN SARGSYAN
BUILDING-Rough-Frame 3/10/2026 Approved HERBERT GIRON
ELECTRICAL-Rough 3/10/2026 Approved HERBERT GIRON
PLUMBING-Rough 3/10/2026 Approved HERBERT GIRON
Insulation 3/17/2026 Corrections Issued KEVIN SARGSYAN
Insulation 3/23/2026 Approved HERBERT GIRON
Drywall Nailing 4/7/2026 Approved KEVIN SARGSYAN