31 S BEVERLY PARK TER 90210

Certificate Information: 31 S BEVERLY PARK TER 90210

Application / Permit
23016-10000-15648
Plan Check / Job No.
B23LA08984
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan 1) Interior major remodel of (E) SFD 2) (N) 16 SF addition to (E) SFD @ first floor 197 SF addition to second floor SFD TO BE SPRINKLERED WITH NFPA13R THRU-OUT
Permit Issued
Issued on 2/27/2024
Issuing Office
Current Status
Issued on 2/27/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/15/2023 APPLICANT
Assigned to Plan Check Engineer 5/18/2023 JAD BASMA
Corrections Issued 5/21/2023 JAD BASMA
Quality Review Completed 5/31/2023 TEODORO DIAZ RODRIGUEZ
Plan Check Approved 2/12/2024 JAD BASMA
Issued 2/27/2024 APPLICANT

Permit Application Clearance Information

Sewer availability Cleared 6/1/2023 LIAM ODONOVAN
ZI Cleared 6/1/2023 JAZMIN ROQUE
Eng Process Fee Ord 176,300 Cleared 6/6/2023 LIAM ODONOVAN
Hydrant and Access approval Cleared 7/7/2023 GILBERT URREA
Grading Pre-Inspection Cleared 9/13/2023 JAD BASMA

Contact Information

Contractor J D Group Inc; Lic. No.: 675485-B       ,

Inspector Information

CARLOS MATAMOROS, (310) 914-3878 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/10/2024 Approved SEAN HAUPT
Footing/Foundation/Slab 9/11/2024 Partial Approval SEAN HAUPT
Reinforced Concrete Frame 9/11/2024 Partial Approval SEAN HAUPT
Excavation/Setback/Form/Re-Bar 10/21/2024 Corrections Issued SEAN HAUPT
Grading Pre-Inspection 10/21/2024 Not Ready for Inspection SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 11/22/2024 Corrections Issued SEAN HAUPT
ELECTRICAL-Rough 1/2/2025 Not Ready for Inspection SEAN HAUPT
Special/Order Compliance 1/13/2025 Corrections Issued MICHAEL PELHAM
Special/Order Compliance 1/27/2025 Partial Approval SEAN HAUPT
Pre-Inspection 6/4/2026 Approved CARLOS MATAMOROS