1244 S CURSON AVE 90019
Certificate Information: 1244 S CURSON AVE 90019
- Application / Permit
- 23016-10000-15633
- Plan Check / Job No.
- B23LA08974
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePLAN. CONVERT (E) DETACHED GARAGE INTO AN ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 6/21/2023
- Issuing Office
- Current Status
- CofO Issued on 5/25/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/15/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/19/2023 | JOHNPAUL ISIP |
| Corrections Issued | 5/20/2023 | JOHNPAUL ISIP |
| Plan Check Approved | 6/21/2023 | KEVIN MORALES |
| Issued | 6/21/2023 | APPLICANT |
| CofO in Progress | 6/14/2024 | ARTHUR NEGRETE |
| No Progress | 4/5/2025 | DEROLD HAUFF |
| CofO in Progress | 4/5/2025 | DEROLD HAUFF |
| CofO in Progress | 5/23/2025 | ARTHUR NEGRETE |
| Permit Finaled | 5/25/2025 | DEROLD HAUFF |
| CofO Issued | 5/25/2025 | DEROLD HAUFF |
| Permit Finaled | 5/25/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/5/2023 | HUGO LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/5/2023 | HUGO LOPEZ |
| Sewer availability | Cleared | 6/5/2023 | HUGO LOPEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 8/9/2023 | No Access for Inspection | JOSE AVILA |
| PLUMBING-Rough | 8/16/2023 | Corrections Issued | JOSE AVILA |
| Special/Order Compliance | 8/16/2023 | Approved | RONNIE MINDANAO |
| Footing/Foundation/Slab | 8/29/2023 | Approved | STUART CHAPMAN |
| ELECTRICAL-Rough | 10/13/2023 | Approved | RONNIE MINDANAO |
| PLUMBING-Rough | 10/13/2023 | Approved | RONNIE MINDANAO |
| ELECTRICAL-Rough | 10/16/2023 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 10/16/2023 | Corrections Issued | JOSE AVILA |
| BUILDING-Rough-Frame | 10/23/2023 | Approved | STUART CHAPMAN |
| Green Building Rough | 10/23/2023 | Not Ready for Inspection | STUART CHAPMAN |
| HVAC-Rough | 10/23/2023 | Approved | STUART CHAPMAN |
| METHANE-Rough | 10/23/2023 | Approved | STUART CHAPMAN |
| Sewer | 10/23/2023 | Approved | STUART CHAPMAN |
| Insulation | 11/2/2023 | Approved | RONNIE MINDANAO |
| Interior/Exterior Lathing | 11/2/2023 | Approved | RONNIE MINDANAO |
| Shower Pan | 11/2/2023 | Approved | RONNIE MINDANAO |
| Drywall Nailing | 11/9/2023 | Approved | CHARLES BOGHOSKHAN |
| Green Building Rough | 11/9/2023 | Approved | CHARLES BOGHOSKHAN |
| Sewer | 11/9/2023 | Approved | CHARLES BOGHOSKHAN |
| Final | 2/28/2024 | Corrections Issued | STUART CHAPMAN |
| Green Building Final | 2/28/2024 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 2/28/2024 | SGSOV Not Ready | STUART CHAPMAN |
| Smoke Detectors | 2/28/2024 | Approved | STUART CHAPMAN |
| Final | 4/24/2024 | Corrections Issued | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 4/24/2024 | SGSOV Approved | RICHARD DOCKUS |
| ELECTRICAL-Final | 6/13/2024 | Approved | ARTHUR NEGRETE |
| Final | 6/13/2024 | OK to Issue CofO | ARTHUR NEGRETE |
| HVAC-Final | 6/13/2024 | Approved | ARTHUR NEGRETE |
| PLUMBING-Final | 6/13/2024 | Approved | ARTHUR NEGRETE |