3414 W 17TH ST 1-9 90019
Certificate Information: 3414 W 17TH ST 1-9 90019
- Application / Permit
- 23016-10000-15602
- Plan Check / Job No.
- B23LA08947
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- EPLAN PROPOSED ADDITION OF ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e)
- Permit Issued
- Issued on 8/16/2024
- Issuing Office
- Current Status
- Issued on 8/16/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/15/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/1/2023 | SINA KHOSRAVI |
| Corrections Issued | 6/8/2023 | SINA KHOSRAVI |
| Quality Review Completed | 6/16/2023 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 9/4/2023 | SINA KHOSRAVI |
| Applicant returned to address corrections | 1/22/2024 | SINA KHOSRAVI |
| Applicant returned to address corrections | 5/24/2024 | SINA KHOSRAVI |
| Applicant returned to address corrections | 6/13/2024 | SINA KHOSRAVI |
| Plan Check Approved | 8/6/2024 | SINA KHOSRAVI |
| Issued | 8/16/2024 | APPLICANT |
Permit Application Clearance Information
| Green Code | Cleared | 6/23/2023 | Rosendo Medina |
| Construction near power lines | Cleared | 1/20/2024 | RIDWAN HARDY |
| Low Impact Development (LID) | Cleared | 3/14/2024 | LUIS CRUZ |
| Roof/Waste drainage to street | Cleared | 3/18/2024 | AMBER CAMPBELL |
| Address approval | Cleared | 3/20/2024 | AMBER CAMPBELL |
| Eng Process Fee Ord 176,300 | Cleared | 3/20/2024 | AMBER CAMPBELL |
| Sewer availability | Cleared | 3/20/2024 | AMBER CAMPBELL |
| Community Plan Implem. Overlay | Cleared | 3/26/2024 | ISAIAH ROSS |
| Tenant Habitability Plan | Cleared | 4/2/2024 | RICARDO BOHORQUEZ |
| Miscellaneous | Cleared | 5/20/2024 | JESSE VIDUYA |
Contact Information
| Contractor | Hershel Construction Inc; Lic. No.: 780613-B | P O BOX 251677 LOS ANGELES, CA 90025 |
| Engineer | Alson,, Ken; Lic. No.: C41697 | 9744 MAPLE ST 201 BELLFLOWER, CA 90706 |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/9/2024 | Conditional Approval | MARTIN TAVITIAN |
| METHANE-Barrier | 9/9/2024 | No Access for Inspection | MARTIN TAVITIAN |
| METHANE-Subgrade | 9/9/2024 | No Access for Inspection | MARTIN TAVITIAN |
| Green Building Rough | 10/2/2024 | Partial Approval | MARTIN TAVITIAN |
| METHANE-Rough | 10/2/2024 | Approved | MARTIN TAVITIAN |
| Wood Frame | 10/2/2024 | Partial Approval | MARTIN TAVITIAN |
| Green Building Rough | 10/8/2024 | Approved | MARTIN TAVITIAN |
| Wood Frame | 10/8/2024 | Partial Approval | MARTIN TAVITIAN |
| Wood Frame | 10/18/2024 | Partial Approval | MARTIN TAVITIAN |
| Interior/Exterior Lathing | 10/28/2024 | Approved | MARTIN TAVITIAN |
| Insulation | 11/7/2024 | Partial Approval | CHRISTOPHER BLACKWOOD |
| Drywall Nailing | 11/13/2024 | Partial Approval | MARTIN TAVITIAN |
| Interior/Exterior Lathing | 12/11/2024 | Partial Approval | CHRISTOPHER BLACKWOOD |
| Final | 8/22/2025 | Not Ready for Inspection | MARTIN TAVITIAN |
| Footing/Foundation/Slab | 8/22/2025 | Approved | MARTIN TAVITIAN |
| Green Building Final | 8/22/2025 | Approved | MARTIN TAVITIAN |
| METHANE-Barrier | 8/22/2025 | Approved | MARTIN TAVITIAN |
| METHANE-Subgrade | 8/22/2025 | Approved | MARTIN TAVITIAN |
| SGSOV-Seismic Gas S/O Valve | 8/22/2025 | SGSOV Approved | MARTIN TAVITIAN |
| Smoke Detectors | 8/22/2025 | Approved | MARTIN TAVITIAN |
| Wood Frame | 8/22/2025 | Approved | MARTIN TAVITIAN |