900-900 1/2 W 52ND ST 90037
Certificate Information: 900-900 1/2 W 52ND ST 90037
- Application / Permit
- 23016-10000-15584
- Plan Check / Job No.
- B23VN05452
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODELING (E) SFD AND CONVERSION OF A PORTION OF (E) SFD TO AN ATTACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e)
- Permit Issued
- Issued on 8/7/2024
- Issuing Office
- Current Status
- Issued on 8/7/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/27/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/11/2023 | CARLOS MONTES |
| Corrections Issued | 5/15/2023 | CARLOS MONTES |
| Quality Review Completed | 5/16/2023 | GARO TELMI |
| Applicant returned to address corrections | 10/19/2023 | CARLOS MONTES |
| Applicant returned to address corrections | 5/31/2024 | CARLOS MONTES |
| Plan Check Approved | 8/1/2024 | CARLOS MONTES |
| Issued | 8/7/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 10/30/2023 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 10/30/2023 | JEANIE LAM |
| Sewer availability | Cleared | 10/30/2023 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 12/12/2023 | JEANIE LAM |
| Construction near power lines | Cleared | 2/21/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yiu,, Siu; Lic. No.: S5801 | PO BOX 1752 TEMPLE CITY, CA 91780 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/30/2025 | Approved | SABAS ALONSO |
| Deputy Wood Construction | 1/31/2025 | Conditional Approval | SABAS ALONSO |
| Deputy Wood Construction | 3/5/2025 | Conditional Approval | SABAS ALONSO |
| Wood Frame | 6/10/2025 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Rough | 6/23/2025 | Conditional Approval | SABAS ALONSO |
| ELECTRICAL-Rough | 6/23/2025 | Corrections Issued | SABAS ALONSO |
| BUILDING-Rough-Frame | 7/1/2025 | Partial Inspection | WAYNE REGESTER |
| PLUMBING-Rough | 7/1/2025 | Corrections Issued | WAYNE REGESTER |
| ELECTRICAL-Rough | 9/22/2025 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 9/22/2025 | Approved | SABAS ALONSO |
| HVAC-Rough | 11/26/2025 | Corrections Issued | SABAS ALONSO |
| Interior/Exterior Lathing | 11/26/2025 | Approved | SABAS ALONSO |
| Shower Pan | 11/26/2025 | Not Ready for Inspection | SABAS ALONSO |
| BUILDING-Rough-Frame | 1/26/2026 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 1/26/2026 | Approved | SABAS ALONSO |
| Green Building Rough | 1/26/2026 | Approved | SABAS ALONSO |
| HVAC-Rough | 1/26/2026 | Approved | SABAS ALONSO |
| Insulation | 4/1/2026 | Approved | SABAS ALONSO |
| Drywall Nailing | 4/16/2026 | Approved | MICHAEL LEWIS |