524 S LORRAINE BLVD 90020
Certificate Information: 524 S LORRAINE BLVD 90020
- Application / Permit
- 23016-10000-15556
- Plan Check / Job No.
- B23LA08908
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ALTERATION AND ADDITION TO EXISTING TWO STORY SINGLE FAMILY RESIDENCE 1 OF 3
- Permit Issued
- Issued on 10/10/2023
- Issuing Office
- Current Status
- CofO Issued on 3/16/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/12/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/1/2023 | CRYSTEL MAALOUF |
| Corrections Issued | 6/12/2023 | CRYSTEL MAALOUF |
| Quality Review Completed | 6/20/2023 | KEN GILL |
| Building Plans Picked Up | 6/28/2023 | APPLICANT |
| Plan Check Approved | 8/9/2023 | CRYSTEL MAALOUF |
| Issued | 10/10/2023 | APPLICANT |
| No Progress | 3/5/2025 | JEFFREY MEAD |
| CofO in Progress | 3/5/2025 | JEFFREY MEAD |
| CofO in Progress | 3/6/2025 | JEFFREY MEAD |
| Permit Finaled | 3/16/2025 | DEROLD HAUFF |
| CofO Issued | 3/16/2025 | DEROLD HAUFF |
| Permit Finaled | 3/16/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| CPC | Cleared | 8/2/2023 | DAMIAN GATTO |
| CPC | Cleared | 8/2/2023 | DAMIAN GATTO |
| CPC | Cleared | 8/2/2023 | DAMIAN GATTO |
| HPOZ | Cleared | 8/2/2023 | DAMIAN GATTO |
| ZI | Cleared | 8/2/2023 | DAMIAN GATTO |
Contact Information
| Architect | Bartholomew,, Lucia; Lic. No.: C37422 | 4116 PINE HOLLOW RD CALABASAS, CA 91302 |
| Contractor | Vallernaud Construction Inc; Lic. No.: 1025929-B | 11513 W PICO BLVD LOS ANGELES, CA 90064 |
| Engineer | Tuchscher,, James Todd; Lic. No.: C77649 | 5503 E 2ND ST LONG BEACH, CA 90803 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/18/2023 | Approved | JEFFREY MEAD |
| Deputy Drilled-In Anchors | 2/6/2024 | Approved | AMIR NAZARIAN |
| Pre-Inspection | 2/7/2024 | Partial Inspection | LILIANA PORTILLO |
| Footing/Foundation/Slab | 2/15/2024 | Partial Approval | JEFFREY MEAD |
| Deputy Reinf. Concrete | 2/16/2024 | Approved | AMIR NAZARIAN |
| Footing/Foundation/Slab | 2/26/2024 | Partial Approval | JEFFREY MEAD |
| Deputy Drilled-In Anchors | 2/29/2024 | Partial Approval | JEFFREY MEAD |
| Deputy Drilled-In Anchors | 3/19/2024 | Partial Approval | JEFFREY MEAD |
| Footing/Foundation/Slab | 3/19/2024 | Partial Approval | JEFFREY MEAD |
| Deputy Drilled-In Anchors | 4/12/2024 | Partial Approval | JEFFREY MEAD |
| Deputy Drilled-In Anchors | 6/6/2024 | Partial Approval | JEFFREY MEAD |
| Deputy Wood Construction | 6/11/2024 | Conditional Approval | RICHARD DOCKUS |
| HVAC-Rough | 7/11/2024 | Corrections Issued | JEFFREY MEAD |
| HVAC-Rough | 7/16/2024 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 7/16/2024 | Partial Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 7/17/2024 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 7/25/2024 | Partial Approval | JEFFREY MEAD |
| Green Building Rough | 7/25/2024 | Not Ready for Inspection | JEFFREY MEAD |
| PLUMBING-Rough | 7/25/2024 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 8/1/2024 | Approved | JEFFREY MEAD |
| Deputy Wood Construction | 8/1/2024 | Conditional Approval | NICHOLAS LOPEZ |
| Green Building Rough | 8/1/2024 | Approved | JEFFREY MEAD |
| Insulation | 8/21/2024 | Approved | JEFFREY MEAD |
| Drywall Nailing | 8/29/2024 | Approved | JEFFREY MEAD |
| Shower Pan | 8/29/2024 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 9/6/2024 | Partial Approval | NICHOLAS LOPEZ |
| Interior/Exterior Lathing | 9/13/2024 | Approved | JOSE MACIAS |
| Interior/Exterior Lathing | 10/4/2024 | Not Ready for Inspection | ANTHONY RAMOS |
| Interior/Exterior Lathing | 11/12/2024 | Approved | NICHOLAS LOPEZ |
| Gas Test | 1/16/2025 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 1/16/2025 | SGSOV Approved | JEFFREY MEAD |
| ELECTRICAL-Final | 2/4/2025 | Corrections Issued | RONNIE MINDANAO |
| PLUMBING-Final | 2/4/2025 | Approved | RONNIE MINDANAO |
| HVAC-Final | 2/6/2025 | Approved | JEFFREY MEAD |
| ELECTRICAL-Final | 2/10/2025 | Approved | JEFFREY MEAD |
| Final | 2/10/2025 | Not Ready for Inspection | JEFFREY MEAD |
| Footing/Foundation/Slab | 2/10/2025 | Approved | JEFFREY MEAD |
| Green Building Final | 2/10/2025 | Approved | JEFFREY MEAD |
| Smoke Detectors | 2/10/2025 | Approved | JEFFREY MEAD |
| Final | 2/14/2025 | Conditional Approval | JEFFREY MEAD |
| Final | 3/6/2025 | OK to Issue CofO | JEFFREY MEAD |