7112 S HARVARD BLVD 1-9 90047
Certificate Information: 7112 S HARVARD BLVD 1-9 90047
- Application / Permit
- 23016-10000-15473
- Plan Check / Job No.
- B23LA08866
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- GROUND FLOOR: ADDITION AND EXPAND OFFICE USE. ADD 3 DWELLING UNITS AND CONVERT TWO CAR GARAGE INTO ADU. 2ND FLOOR:NO WORK (TOTAL NEW 8 UNITS)
- Permit Issued
- Issued on 8/19/2025
- Issuing Office
- Current Status
- Issued on 8/19/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/12/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/18/2023 | JOE VO |
| Corrections Issued | 5/20/2023 | JOE VO |
| Quality Review Completed | 6/2/2023 | JOHN FRANCIA |
| Applicant returned to address corrections | 4/15/2025 | JOE VO |
| Plan Check Approved | 4/16/2025 | JOE VO |
| Issued | 8/19/2025 | APPLICANT |
Permit Application Clearance Information
| Permit | Cleared | 6/29/2023 | TREVOR QUAN |
| Historic Resource Verification | Cleared | 3/11/2024 | RAFAEL FONTES |
| Address approval | Cleared | 3/13/2024 | KEVIN AVILA |
| Highway dedication | Cleared | 3/13/2024 | KEVIN AVILA |
| Roof/Waste drainage to street | Cleared | 3/13/2024 | KEVIN AVILA |
| Fire Marshal Fire Life Safety | Cleared | 3/18/2024 | WILLIAM JOHNS |
| Green Code | Cleared | 11/7/2024 | AARON COSTA |
| Hydrant and Access approval | Cleared | 11/21/2024 | KURT CORRAL |
| Tenant Habitability Plan | Cleared | 1/14/2025 | RICARDO BOHORQUEZ |
| SB8 RUD | Cleared | 3/11/2025 | JAMES MCCARTHY |
| Community Plan Implem. Overlay | Cleared | 3/24/2025 | MANERI ROMAN |
| DAS Clearance | Cleared | 3/24/2025 | Hernan Arreola |
| Sewer availability | Cleared | 3/25/2025 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 4/3/2025 | WALLIE JONG |
| Redevelopment Project Area | Cleared | 4/3/2025 | YASMINE BASHIRI |
| Miscellaneous | Cleared | 4/16/2025 | JOE VO |
Contact Information
| Contractor | Line Electric Inc; Lic. No.: 910172-B | , |
| Engineer | Pineda,, Salvador Antonio; Lic. No.: S5233 | 560 W MAIN STREET SUITE C-328 ALHAMBRA, CA 91801 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/16/2025 | Corrections Issued | DARRYL ARNOLD |
| Footing/Foundation/Slab | 9/30/2025 | Corrections Issued | ALFREDO LOPEZ |
| Special/Order Compliance | 10/2/2025 | Partial Approval | ALFREDO LOPEZ |
| Drywall Nailing | 10/20/2025 | Partial Approval | ALFREDO LOPEZ |
| Footing/Foundation/Slab | 10/24/2025 | Partial Approval | ALFREDO LOPEZ |
| Insulation | 10/24/2025 | Partial Approval | ALFREDO LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 11/5/2025 | Conditional Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 11/25/2025 | Approved | ALFREDO LOPEZ |
| Insulation | 12/19/2025 | Partial Inspection | JEFFREY FULTON |
| Drywall Nailing | 12/29/2025 | Approved | ALFREDO LOPEZ |
| Final | 6/17/2026 | Partial Inspection | ALFREDO LOPEZ |
| Footing/Foundation/Slab | 6/17/2026 | Approved | ALFREDO LOPEZ |
| Green Building Final | 6/17/2026 | Approved | ALFREDO LOPEZ |
| Green Building Rough | 6/17/2026 | Approved | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 6/17/2026 | SGSOV Approved | ALFREDO LOPEZ |
| Smoke Detectors | 6/17/2026 | Not Ready for Inspection | ALFREDO LOPEZ |
| Wood Frame | 6/17/2026 | Approved | ALFREDO LOPEZ |