157 N VISTA ST 90036

Certificate Information: 157 N VISTA ST 90036

Application / Permit
23016-10000-15448
Plan Check / Job No.
B23LA08853
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL OF (E) 2-STORY SINGLE FAMILY DWELLING TO CREATE LARGER OPENINGS FOR LIVING ROOM, DINING ROOM, FAMILY ROOM, AND KITCHEN TO CONNECT. WORK DONE PER ENGINEER.
Permit Issued
Issued on 6/21/2023
Issuing Office
Current Status
Permit Finaled on 8/29/2024

Permit Application Status History

Submitted 5/12/2023 APPLICANT
Assigned to Plan Check Engineer 5/12/2023 MADISON ODELL
Corrections Issued 5/30/2023 MADISON ODELL
Plan Check Approved 6/14/2023 MADISON ODELL
Issued 6/21/2023 APPLICANT
Permit Finaled 8/29/2024 JUSTIN HAWLEY

Permit Application Clearance Information

Sewer availability Cleared 5/31/2023 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 6/1/2023 JEANIE LAM
HPOZ Cleared 6/5/2023 DAMIAN GATTO
ZI Cleared 6/5/2023 DAMIAN GATTO
ZI Cleared 6/5/2023 DAMIAN GATTO

Contact Information

Contractor Owner-Builder       ,
Engineer Hernandez,, Gerardo; Lic. No.: C78115 1426 E STUART AVE      WEST COVINA, CA 91791

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/17/2023 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 9/11/2023 Not Ready for Inspection LILIANA PORTILLO
ELECTRICAL-Rough 9/11/2023 Corrections Issued LILIANA PORTILLO
Gas Test 9/11/2023 Approved LILIANA PORTILLO
HVAC-Rough 9/11/2023 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 9/11/2023 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Rough 9/12/2023 Not Ready for Inspection LILIANA PORTILLO
HVAC-Rough 9/12/2023 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Rough 9/12/2023 Not Ready for Inspection LILIANA PORTILLO
Sewer 9/12/2023 Not Ready for Inspection LILIANA PORTILLO
BUILDING-Rough-Frame 10/3/2023 Approved LILIANA PORTILLO
ELECTRICAL-Rough 10/3/2023 Approved LILIANA PORTILLO
HVAC-Rough 10/3/2023 Approved LILIANA PORTILLO
PLUMBING-Rough 10/3/2023 Approved LILIANA PORTILLO
Insulation 10/5/2023 Approved LILIANA PORTILLO
Drywall Nailing 10/16/2023 Approved LILIANA PORTILLO
Shower Pan 10/16/2023 Approved LILIANA PORTILLO
Interior/Exterior Lathing 10/24/2023 Approved LILIANA PORTILLO
Special/Order Compliance 7/12/2024 Corrections Issued AMIR NAZARIAN
Final 7/29/2024 Corrections Issued AMIR NAZARIAN
SGSOV-Seismic Gas S/O Valve 7/29/2024 SGSOV Approved AMIR NAZARIAN
Smoke Detectors 7/29/2024 Approved AMIR NAZARIAN
Final 8/26/2024 Corrections Issued ENRIQUE MIRELES
Final 8/29/2024 Permit Finaled JUSTIN HAWLEY