157 N VISTA ST 90036
Certificate Information: 157 N VISTA ST 90036
- Application / Permit
- 23016-10000-15448
- Plan Check / Job No.
- B23LA08853
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL OF (E) 2-STORY SINGLE FAMILY DWELLING TO CREATE LARGER OPENINGS FOR LIVING ROOM, DINING ROOM, FAMILY ROOM, AND KITCHEN TO CONNECT. WORK DONE PER ENGINEER.
- Permit Issued
- Issued on 6/21/2023
- Issuing Office
- Current Status
- Permit Finaled on 8/29/2024
Permit Application Status History
| Submitted | 5/12/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/12/2023 | MADISON ODELL |
| Corrections Issued | 5/30/2023 | MADISON ODELL |
| Plan Check Approved | 6/14/2023 | MADISON ODELL |
| Issued | 6/21/2023 | APPLICANT |
| Permit Finaled | 8/29/2024 | JUSTIN HAWLEY |
Permit Application Clearance Information
| Sewer availability | Cleared | 5/31/2023 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 6/1/2023 | JEANIE LAM |
| HPOZ | Cleared | 6/5/2023 | DAMIAN GATTO |
| ZI | Cleared | 6/5/2023 | DAMIAN GATTO |
| ZI | Cleared | 6/5/2023 | DAMIAN GATTO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hernandez,, Gerardo; Lic. No.: C78115 | 1426 E STUART AVE WEST COVINA, CA 91791 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/17/2023 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 9/11/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Rough | 9/11/2023 | Corrections Issued | LILIANA PORTILLO |
| Gas Test | 9/11/2023 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 9/11/2023 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 9/11/2023 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Rough | 9/12/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| HVAC-Rough | 9/12/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| PLUMBING-Rough | 9/12/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| Sewer | 9/12/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 10/3/2023 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Rough | 10/3/2023 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 10/3/2023 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 10/3/2023 | Approved | LILIANA PORTILLO |
| Insulation | 10/5/2023 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 10/16/2023 | Approved | LILIANA PORTILLO |
| Shower Pan | 10/16/2023 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 10/24/2023 | Approved | LILIANA PORTILLO |
| Special/Order Compliance | 7/12/2024 | Corrections Issued | AMIR NAZARIAN |
| Final | 7/29/2024 | Corrections Issued | AMIR NAZARIAN |
| SGSOV-Seismic Gas S/O Valve | 7/29/2024 | SGSOV Approved | AMIR NAZARIAN |
| Smoke Detectors | 7/29/2024 | Approved | AMIR NAZARIAN |
| Final | 8/26/2024 | Corrections Issued | ENRIQUE MIRELES |
| Final | 8/29/2024 | Permit Finaled | JUSTIN HAWLEY |