757 S ALAMEDA ST Suite 600 90021
Certificate Information: 757 S ALAMEDA ST Suite 600 90021
- Application / Permit
- 23016-10000-15289
- Plan Check / Job No.
- B23LA08748
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- ePLAN. SCOPE OF WORK ON THE 6TH FLOOR SHALL CONSIST OF NEW PARTITIONS, DOORS, FINISHES, CEILINGS, LIGHTING, MILLWORK, PLUMBING,
- Permit Issued
- Issued on 9/7/2023
- Issuing Office
- Current Status
- Permit Finaled on 2/4/2025
Permit Application Status History
| Submitted | 5/11/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/25/2023 | ARSALAN SHABESTARI |
| Corrections Issued | 6/19/2023 | ARSALAN SHABESTARI |
| Quality Review Completed | 6/23/2023 | GARO TELMI |
| Plan Check Approved | 9/1/2023 | ARSALAN SHABESTARI |
| Issued | 9/7/2023 | APPLICANT |
| Permit Finaled | 2/4/2025 | PAUL BAZERKANIAN |
Permit Application Clearance Information
| Green Code | Cleared | 7/24/2023 | AARON COSTA |
| Fire Marshal Fire Life Safety | Cleared | 8/3/2023 | FIRE DEPARTMENT |
| DAS Clearance | Cleared | 8/7/2023 | Kevin Morales |
| City Hist. Cultural Monument | Cleared | 8/22/2023 | MAX LODER |
| Historic Resource Verification | Cleared | 8/22/2023 | MAX LODER |
| Historic monument | Cleared | 8/22/2023 | MAX LODER |
| Redevelopment Project Area | Cleared | 9/1/2023 | DAVID URITA |
Contact Information
| Contractor | S P C Industries Inc; Lic. No.: 433163-B | , |
| Contractor | Sierra Pacific Constructors Inc; Lic. No.: 433163-B | , |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/20/2023 | Approved | KATY RAMIREZ |
| Drywall Nailing | 1/2/2024 | Partial Approval | JEROME BLACKWOOD |
| Insulation | 1/2/2024 | Partial Approval | JEROME BLACKWOOD |
| Light Gage Steel Frame | 1/2/2024 | Partial Approval | JEROME BLACKWOOD |
| Drywall Nailing | 1/16/2024 | Partial Inspection | KATY RAMIREZ |
| Insulation | 1/22/2024 | Partial Approval | KATY RAMIREZ |
| Drywall Nailing | 1/31/2024 | Partial Approval | KATY RAMIREZ |
| Light Gage Steel Frame | 2/13/2024 | Partial Approval | KATY RAMIREZ |
| Drywall Nailing | 2/26/2024 | No Access for Inspection | LUIS CCAMACHO |
| Drywall Nailing | 2/28/2024 | Partial Approval | LUIS CCAMACHO |
| Drywall Nailing | 3/4/2024 | Partial Approval | LUIS CCAMACHO |
| Light Gage Steel Frame | 3/4/2024 | Partial Approval | LUIS CCAMACHO |
| Drywall Nailing | 3/8/2024 | Not Ready for Inspection | RONALD JIMENEZ |
| Light Gage Steel Frame | 3/8/2024 | Partial Approval | RONALD JIMENEZ |
| Drywall Nailing | 3/12/2024 | Partial Approval | JEROME BLACKWOOD |
| Light Gage Steel Frame | 3/20/2024 | Partial Approval | LUIS CCAMACHO |
| Drywall Nailing | 3/21/2024 | Partial Approval | LUIS CCAMACHO |
| Drywall Nailing | 3/22/2024 | Partial Approval | LUIS CCAMACHO |
| Light Gage Steel Frame | 4/1/2024 | Partial Approval | NICK DANERI |
| Drywall Nailing | 4/5/2024 | Not Ready for Inspection | LUIS CCAMACHO |
| Light Gage Steel Frame | 4/5/2024 | Corrections Issued | LUIS CCAMACHO |
| T-Bar Ceiling | 4/26/2024 | Partial Approval | LUIS CCAMACHO |
| Light Gage Steel Frame | 4/29/2024 | Partial Approval | LUIS CCAMACHO |
| Final | 11/15/2024 | Not Ready for Inspection | RAFAEL CORTES |
| Green Building Final | 11/15/2024 | Not Ready for Inspection | RAFAEL CORTES |
| SGSOV-Seismic Gas S/O Valve | 11/15/2024 | SGSOV Not Ready | RAFAEL CORTES |
| Smoke Detectors | 11/15/2024 | Approved | RAFAEL CORTES |
| Final | 2/4/2025 | Permit Finaled | PAUL BAZERKANIAN |
| Green Building Final | 2/4/2025 | Approved | PAUL BAZERKANIAN |
| SGSOV-Seismic Gas S/O Valve | 2/4/2025 | SGSOV Approved | PAUL BAZERKANIAN |