4851 W ADAMS BLVD 90016

Certificate Information: 4851 W ADAMS BLVD 90016

Application / Permit
23016-10000-15014
Plan Check / Job No.
B23LA08576
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Retail
Work Description
REPLACE PORTION OF EXISTING FACADE OF EXISTING URM BUILDING TO NEW CONCRETE FACADE.
Permit Issued
Issued on 9/7/2023
Issuing Office
West Los Angeles
Current Status
Permit Finaled on 5/29/2025

Permit Application Status History

Submitted 5/9/2023 APPLICANT
Assigned to Plan Check Engineer 5/11/2023 YOUNG KIM
Corrections Issued 5/15/2023 YOUNG KIM
Quality Review Completed 5/19/2023 KEN GILL
Building Plans Picked Up 5/25/2023 APPLICANT
Disabled Access Plans Picked Up 6/9/2023 APPLICANT
Plan Check Approved 9/5/2023 YOUNG KIM
Issued 9/7/2023 APPLICANT
Permit Finaled 5/29/2025 MARTIN TAVITIAN

Permit Application Clearance Information

Historic Resource Verification Cleared 5/31/2023 MAX LODER
ZA Case Cleared 7/7/2023 EDWIN CANO
Community Plan Implem. Overlay Cleared 7/11/2023 KYLE WINSTON
Redevelopment Project Area Cleared 7/12/2023 CARTER HOWE
DAS Clearance Cleared 8/31/2023 YOUNG KIM

Contact Information

Contractor Mac Donald General Contracting Inc; Lic. No.: 467384-B 1339 WALGROVE AVENUE      MAR VISTA, CA 90066
Engineer Koma,, Shahram Javadi; Lic. No.: C69497 23241 VENTURA BLVD 300      WOODLAND HILLS, CA 91364

Inspector Information

IAN BLINN, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI
CHRISTOPHER BLACKWOOD, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/4/2023 Partial Approval ALFREDO LOPEZ
Excavation/Setback/Form/Re-Bar 10/6/2023 Partial Approval VAHE KELEDJIAN
Wood Frame 11/1/2023 Partial Inspection ALFREDO LOPEZ
Excavation/Setback/Form/Re-Bar 11/20/2023 Partial Approval RICARDO ROBLES
Excavation/Setback/Form/Re-Bar 11/27/2023 Partial Approval RICARDO ROBLES
Wood Frame 2/9/2024 Partial Approval RICARDO ROBLES
Insulation 4/2/2024 Partial Approval JACOB MYERS
Interior/Exterior Lathing 4/11/2024 Approved MARTIN TAVITIAN
Interior/Exterior Lathing 6/11/2024 Partial Approval JACOB MYERS
Final 5/29/2025 Permit Finaled MARTIN TAVITIAN
SGSOV-Seismic Gas S/O Valve 5/29/2025 SGSOV Approved MARTIN TAVITIAN
Smoke Detectors 5/29/2025 Approved MARTIN TAVITIAN